Decree of the Russian government on the transfer of electrical power. Legislative framework of the Russian Federation

Rules for access to electricity transmission services - Russian newspaper. In order to promote competition in the production and sales market electrical energy, protection of the rights of consumers of electrical energy and in accordance with Articles 2. Federal Law.

Approve the attached: Rules for non-discriminatory access to services for the transmission of electrical energy and the provision of these services; Rules for non-discriminatory access to services for operational dispatch control in the electric power industry and the provision of these services; Rules for non-discriminatory access to the services of the administrator of the wholesale market trading system and the provision of these services; Rules technological connection energy receiving devices (power installations) of legal entities and individuals to electrical networks. Designate the Federal Antimonopoly Service as the authorized federal executive body to ensure state control for compliance with the Rules of non-discriminatory access to electric energy transmission services, operational dispatch control services in the electric power industry and services of a trading system administrator. The Ministry of Industry and Energy of the Russian Federation, within 3 months, must develop and approve a methodology for determining standard and actual losses of electrical energy in electrical networks. Chairman of the Government. Russian Federation. M. Fradkov. Rules for non-discriminatory access to electric energy transmission services and the provision of these services. I. General provisions.

These Rules define general principles and the procedure for ensuring non-discriminatory access to electric energy transmission services, as well as the provision of these services. The terms used in these Rules mean the following.

Non-discriminatory access to electric energy transmission services involves ensuring equal conditions for the provision of these services to their consumers, regardless of organizational and legal forms and legal relations with the person providing these services. Grid organizations are required to disclose information regarding access to electric energy transmission services and the provision of these services in accordance with the standards for information disclosure by subjects of the wholesale and retail electric energy markets. These Rules do not apply to relations related to the provision of intersystem electrical connections, unless otherwise provided by the legislation of the Russian Federation. Services for the transmission of electrical energy are provided by the network organization on the basis of an agreement on the paid provision of services for the transmission of electrical energy to persons who, by right of ownership or on another legal basis, have power receiving devices and other electric power facilities technologically connected in the prescribed manner to the electrical network, as well as subjects of wholesale electricity market, exporting (importing) electricity, energy sales organizations and guaranteeing suppliers. The grid organization, in fulfillment of its obligations to consumers of services under the contract for the provision of services for the transmission of electrical energy (hereinafter referred to as the contract), is obliged to regulate relations for the provision of intersystem electrical connections with other grid organizations that have technological connections to electrical networks owned or otherwise legally owned basis from this network organization, in the manner prescribed by the legislation of the Russian Federation. During the transition period of operation of the electric power industry, the provision of services for the transmission of electrical energy using facilities included in the unified national (all-Russian) electrical network is carried out on the basis of an agreement concluded both on behalf of the organization for managing the unified national (all-Russian) electrical network and on behalf of others owners of these objects.

  1. RULES FOR TECHNOLOGICAL POWER SUPPLY technological connection and.
  2. Decree of the Government of the Russian Federation of December 27, 2004 N 861 (ed.
  3. Government Decree. Russian Federation dated December 27, 2004 TECHNOLOGICAL CONNECTION.

II. The procedure for concluding and executing the contract. The agreement is public and mandatory for the network organization. Unreasonable evasion or refusal by a network organization to conclude an agreement may be appealed by the consumer of services in the manner established by the legislation of the Russian Federation. An agreement cannot be concluded before the conclusion of an agreement on the technological connection of energy receiving devices (power installations) of legal entities and individuals to electric networks, with the exception of cases where the consumer of services is: a person whose energy receiving device was technologically connected to the electric network before entry into force these Rules; a person who exports (imports) electrical energy and does not own, use or dispose of electrical power facilities connected to the electrical network; an energy sales organization (supplier of last resort) that enters into an agreement in the interests of the consumers of electrical energy it serves. In relation to these persons, the network organization has the right, in order to determine the technical characteristics of power receiving devices (power installations) necessary for the provision of services for the transmission of electrical energy, to request information and documentation necessary for technological connection. Under the contract, the network organization undertakes to carry out a set of organizationally and technologically related actions that ensure the transmission of electrical energy through technical devices of electrical networks, and the consumer of services - to pay for them. The contract must contain the following essential conditions: the maximum power value of the power receiving device connected to the electrical network, with the distribution of this value for each connection point of the electrical network in respect of which technological connection was made in the manner established by the legislation of the Russian Federation; the amount of power (generating or consumed) within which the network organization undertakes to ensure the transmission of electrical energy at the connection points specified in the contract; responsibility of the service consumer and the network organization for the condition and maintenance of electric grid facilities, which is determined by their balance sheet and is recorded in the act of delimitation of the balance sheet of electric grids and the operational responsibilities of the parties attached to the contract; the amount of technological and emergency reservation (for consumers - legal entities or entrepreneurs without forming a legal entity who meet the relevant requirements established by the legislation of the Russian Federation in the field of electric power industry), which must be taken into account when determining the procedure for limiting the power consumption regime.

For these persons, the act of approval of emergency and technological armor is a mandatory annex to the contract; obligations of the parties to equip connection points with means of measuring electrical energy, including measuring instruments that comply with the requirements established by the legislation of the Russian Federation, as well as ensuring their operability and compliance during the entire term of the contract with operational requirements for them established by the authorized body for technical regulation and metrology and the manufacturer. The consumer of services assumes the following obligations in accordance with the contract: to pay the network organization for services for the transmission of electrical energy within the terms and amounts established by the contract; maintain the relay protection and emergency automation equipment, electricity and power metering devices, as well as other devices necessary to maintain the required parameters of reliability and quality of electricity, which are in his possession or on another legal basis, and comply with the requirements during the entire term of the contract , established for technological connection and in the operating rules of the specified means, instruments and devices; submit to the network organization, within the time limits established by the contract, the necessary technological information: main electrical diagrams, equipment characteristics, diagrams of relay protection devices and emergency automation, operational data on the technological operating modes of the equipment; inform the network organization within the time limits established by the contract about emergencies at energy facilities, planned, current and major renovation on them; inform the network organization about the scope of participation in automatic or operational emergency power control, in normalized primary frequency regulation and in secondary power regulation (for power plants), as well as about the list and power of the service consumer's current collectors that can be turned off by emergency automatic devices; fulfill obligations to ensure the safe operation of energy networks under their control and the serviceability of the instruments and equipment they use related to the transmission of electrical energy; freely admit authorized representatives of the grid organization to the points of control and recording of the quantity and quality of transferred electrical energy in the manner established by the agreement.

861 Decree of the Government of the Russian Federation On Electric Power Industry

N 740 “On amendments to the Decree of the Government of the Russian Federation of December 27, 2004 N 861 for the purpose of clarification. Government Decree. Russian Federation dated December 27, 2004 TECHNOLOGICAL CONNECTION. For the operation of relevant energy receiving devices and power grid facilities; Decree of the Government of the Russian Federation of December 27, 2004 N 861 (ed. Page 1 of 129. Decree of the Government of the Russian Federation of December 27, 2004 N 861 (ed. Document provided by ConsultantPlus Date saved: 04/14/2017.

"On approval of the Rules for non-discriminatory access to services for the transmission of electrical energy and the provision of these services,
Rules of non-discriminatory access to services for operational dispatch control in the electric power industry and the provision of these services, Rules of non-discriminatory access to the services of the administrator of the wholesale market trading system and the provision of these services and
Rules for technological connection of power receiving devices (power installations)
legal entities and individuals to electrical networks"

In order to promote the development of competition in the market for the production and sale of electrical energy, to protect the rights of consumers of electrical energy and in accordance with Articles 20, 21, 25 and 26 of the Federal Law "On Electric Power Industry", the Government of the Russian Federation decides:

1. Approve the attached:

Rules for non-discriminatory access to electric energy transmission services and the provision of these services;

Rules for non-discriminatory access to services for operational dispatch control in the electric power industry and the provision of these services;

Rules for non-discriminatory access to the services of the administrator of the wholesale market trading system and the provision of these services;

Rules for the technological connection of energy receiving devices (power installations) of legal entities and individuals to electrical networks.

2. Designate the Federal Antimonopoly Service as the authorized federal executive body to ensure state control over compliance with the rules of non-discriminatory access to electric energy transmission services, operational dispatch management services in the electric power industry and trading system administrator services.

3. The Ministry of Industry and Energy of the Russian Federation, within 3 months, develop and approve a methodology for determining standard and actual losses of electrical energy in electrical networks.

Chairman of the Government of the Russian Federation M. Fradkov

Rules
non-discriminatory access to electric energy transmission services and provision of these services

I. General provisions

1. These Rules define the general principles and procedure for ensuring non-discriminatory access to electric energy transmission services, as well as the provision of these services.

2. The terms used in these Rules mean the following:

“territorial distribution network” - a complex of power lines and equipment not included in the unified national (all-Russian) electrical network used to provide services for the transmission of electrical energy;

“grid organizations” - commercial organizations whose main activity is the provision of services for the transmission of electrical energy through electrical networks, as well as the implementation of technological connection activities;

“point of connection to the electrical network” - the place of physical connection of the power receiving device (power installation) (hereinafter referred to as the power receiving device) of the consumer of electric energy transmission services (hereinafter referred to as the consumer of services) with the electrical network of the network organization;

“electric network throughput” is the technologically maximum permissible value of power that can be transmitted taking into account operating conditions and reliability parameters of the functioning of electric power systems;

“balance sheet boundary” is the line of dividing electric grid facilities between owners on the basis of ownership or possession on another legal basis.

Other concepts used in these Rules correspond to the concepts defined by the legislation of the Russian Federation.

3. Non-discriminatory access to electric energy transmission services provides for ensuring equal conditions for the provision of these services to their consumers, regardless of organizational legal form and legal relations with the person providing these services.

4. Grid organizations are required to disclose information regarding access to electric energy transmission services and the provision of these services in accordance with the standards for information disclosure by subjects of the wholesale and retail electric energy markets.

5. These Rules do not apply to relations related to the provision of intersystem electrical connections, unless otherwise provided by the legislation of the Russian Federation.

6. Services for the transmission of electrical energy are provided by the network organization on the basis of an agreement on the paid provision of services for the transmission of electrical energy to persons who, by right of ownership or on another legal basis, have power receiving devices and other electric power facilities technologically connected in the prescribed manner to the electrical network, as well as subjects of the wholesale electricity market exporting (importing) electricity, energy sales organizations and guaranteeing suppliers.

7. The grid organization, in fulfillment of its obligations to consumers of services under the contract for the provision of services for the transmission of electrical energy (hereinafter referred to as the contract), is obliged to regulate relations for the provision of intersystem electrical connections with other grid organizations that have technological connections to electrical networks owned or controlled by on another legal basis for this network organization, in the manner prescribed by the legislation of the Russian Federation.

8. During the transition period of operation of the electric power industry, the provision of services for the transmission of electrical energy using facilities included in the unified national (all-Russian) electrical network is carried out on the basis of an agreement concluded both on behalf of the organization for managing the unified national (all-Russian) electrical network, and from on behalf of other owners of these objects.

II. The procedure for concluding and executing an agreement

9. The agreement is public and mandatory for the network organization.

Unreasonable evasion or refusal by a network organization to conclude an agreement may be appealed by the consumer of services in the manner established by the legislation of the Russian Federation.

10. An agreement cannot be concluded before the conclusion of an agreement on the technological connection of energy receiving devices (power installations) of legal entities and individuals to electrical networks, except for cases where the consumer of services is:

a person whose power receiving device was technologically connected to the electrical network before these Rules came into force;

a person who exports (imports) electrical energy and does not own, use or dispose of electrical power facilities connected to the electrical network;

an energy sales organization (supplier of last resort) that enters into an agreement in the interests of the consumers of electrical energy it serves.

In relation to these persons, the network organization has the right, in order to determine the technical characteristics of power receiving devices (power installations) necessary for the provision of services for the transmission of electrical energy, to request information and documentation necessary for technological connection.

11. Under the contract, the network organization undertakes to carry out a set of organizationally and technologically related actions that ensure the transmission of electrical energy through technical devices of electrical networks, and the consumer of services - to pay for them.

12. The contract must contain the following essential terms:

the maximum power value of the power receiving device connected to the electrical network, with the distribution of the specified value for each connection point of the electrical network in respect of which technological connection was carried out in the manner established by the legislation of the Russian Federation;

the amount of power (generating or consumed) within which the network organization undertakes to ensure the transmission of electrical energy at the connection points specified in the contract;

responsibility of the service consumer and the network organization for the condition and maintenance of electric grid facilities, which is determined by their balance sheet and is recorded in the act of delimitation of the balance sheet of electric grids and the operational responsibilities of the parties attached to the contract;

the amount of technological and emergency reservation (for consumers - legal entities or entrepreneurs without forming a legal entity who meet the relevant requirements established by the legislation of the Russian Federation in the field of electric power industry), which must be taken into account when determining the procedure for limiting the power consumption regime. For these persons, the act of approval of emergency and technological armor is a mandatory annex to the contract;

obligations of the parties to equip connection points with means of measuring electrical energy, including measuring instruments that comply with the requirements established by the legislation of the Russian Federation, as well as ensuring their operability and compliance during the entire term of the contract with operational requirements for them established by the authorized body for technical regulation and metrology and the manufacturer.

13. The service consumer assumes the following obligations in accordance with the contract:

pay the network organization for services for the transmission of electrical energy within the terms and amounts established by the contract;

maintain the relay protection and emergency automation equipment, electricity and power metering devices, as well as other devices necessary to maintain the required parameters of reliability and quality of electricity, which are in his possession or on another legal basis, and comply with the requirements during the entire term of the contract , established for technological connection and in the operating rules of the specified means, instruments and devices;

submit to the network organization, within the time limits established by the contract, the necessary technological information: main electrical diagrams, equipment characteristics, diagrams of relay protection devices and emergency automation, operational data on the technological operating modes of the equipment;

inform the network organization within the time limits established by the contract about emergencies at energy facilities, planned, current and major repairs at them;

inform the network organization about the scope of participation in automatic or operational emergency power control, in normalized primary frequency regulation and in secondary power regulation (for power plants), as well as about the list and power of the service consumer's current collectors that can be turned off by emergency automatic devices;

fulfill obligations to ensure the safe operation of energy networks under their control and the serviceability of the instruments and equipment they use related to the transmission of electrical energy;

freely admit authorized representatives of the grid organization to the points of control and recording of the quantity and quality of transferred electrical energy in the manner established by the agreement.

14. The grid organization assumes the following obligations in accordance with the agreement:

ensure the transfer of electrical energy to the energy receiving devices of the service consumer, the quality and parameters of which must comply with technical regulations and other mandatory requirements;

carry out the transfer of electrical energy in accordance with the agreed reliability parameters, taking into account the technological characteristics of power receiving devices (power plants);

in the manner and within the time limits established by the contract, inform the service consumer about emergencies in electrical networks, repair and maintenance work that affect the fulfillment of obligations under the contract;

freely admit authorized representatives of service consumers to points of control and recording of the quantity and quality of transferred electrical energy in the manner established by the contract.

15. A person who intends to conclude an agreement (hereinafter referred to as the applicant) sends a written application to the network organization to conclude an agreement, which must contain the following information:

details of the consumer of electric energy transmission services;

volumes and expected mode of transmission of electrical energy broken down by month;

the volume of maximum power and the nature of the load of energy receiving devices (power plants) connected to the network (generating or consumed), with its distribution at each point of connection of the electrical network and indicating the boundaries of the balance sheet;

single-line diagram of the electrical network of a service consumer connected to the networks of a network organization;

points of connection to the networks of the network organization, indicating for each point of connection to the network the declared power values, including the power values ​​during the period of maximum loads of electrical energy consumers;

start date for the provision of electricity transmission services;

reference to the agreement on the provision of services for operational dispatch control (in the case of concluding an agreement on the provision of services for the transmission of electrical energy with an organization for managing the unified national (all-Russian) electrical grid).

16. The network organization, within 30 days from the date of receipt of the application for concluding an agreement, is obliged to consider it and send the applicant a draft agreement signed by the network organization or a reasoned refusal to conclude it.

17. In the absence of information specified in paragraph 15 of these Rules, the network organization notifies the applicant about this within 6 working days and, within 30 days from the date of receipt of the missing information, considers the application in accordance with paragraph 16 of these Rules.

18. The applicant, who has received a draft agreement from the network organization, fills it out in the part related to the information about the applicant included in the agreement, and sends one signed copy of the agreement to the network organization.

19. The agreement is considered concluded from the date it is signed by the applicant, unless otherwise established by the agreement or court decision.

20. The grid organization has the right to refuse to conclude an agreement in the event of:

the consumer of services does not have a concluded agreement on the provision of services for operational dispatch control (in the case of concluding an agreement on the provision of services for the transmission of electrical energy with an organization for managing the unified national (all-Russian) electrical grid);

lack of technical capability to provide services for the transmission of electrical energy in the declared volume (if the volume of power is declared, the proper transmission of which cannot be ensured by the grid organization based on the existing conditions of technological connection);

sending an application to conclude an agreement by a person who does not have a technological connection to the electrical networks of this network organization. At the same time, a mandatory condition for concluding an agreement with guaranteeing suppliers and energy sales organizations is the presence of a technological connection of consumers of electrical energy in whose favor the agreement is concluded, and for organizations engaged in the export-import of electrical energy, the presence of a connection between the electrical networks of this network organization and the electrical networks neighboring states through whose territories export and import supplies of electrical energy are carried out.

21. If it is not technically possible to provide services for the transmission of electrical energy within the scope of services declared by the consumer, the network organization is obliged to notify the applicant within 30 days about the conditions and to what extent the service can be provided and the contract can be concluded.

22. If there are grounds for refusal to conclude an agreement, the network organization is obliged, no later than 30 days from the date of receipt of the application specified in paragraph 15 of these Rules, to send to the applicant in writing a reasoned refusal to conclude an agreement with supporting documents attached.

Refusal to conclude an agreement may be challenged in the manner established by the legislation of the Russian Federation.

23. Required condition to provide services for the transmission of electrical energy to the consumer of services, it is necessary that he has the status of a participant in the wholesale market or has concluded an electrical energy purchase and sale agreement with a guaranteeing supplier, energy sales organization or other supplier of electrical energy.

24. The grid organization has the right to suspend the transmission of electrical energy in the following cases:

the occurrence of debt of the consumer of services to pay for electric energy transmission services for 2 or more billing periods;

violation by the consumer of the terms of payment for services for the transmission of electrical energy, defined in the purchase and sale agreement concluded by him (agreement on accession to the wholesale electricity (capacity) market), - in the presence of appropriate notification in writing from the administrator of the trading system, the guaranteeing supplier or the energy sales organization with the attachment of supporting documents indicating the amount of the consumer’s debt confirmed by a reconciliation act or a court decision, the deadline for its repayment, as well as the expected period for introducing restrictions on the consumption regime;

connection by the consumer of services to the electrical network of power receiving devices (power installations) that do not comply with the terms of the contract, or connection carried out in violation of the procedure for technological connection of power receiving devices of legal entities and individuals to electrical networks.

25. The transmission of electrical energy is suspended in the event of:

the absence or expiration of the obligation of the supplier (seller) of electrical energy to the consumer under the supply agreement (purchase and sale, energy supply, etc.) of electrical energy (power), which must be transmitted through the networks of the network organization;

termination of the participation of the service consumer in the wholesale market, of which the network organization must be notified in writing by the electricity supplier or the administrator of the trading system, indicating the grounds, at least 10 days before the date of termination of these obligations. Such notification is sent to the consumer at the same time.

26. Suspension of the transmission of electrical energy does not entail termination of the contract.

When the transmission of electrical energy is suspended on the grounds provided for in paragraph 24 of these Rules, consumers of services are allowed to partially or completely limit the mode of consumption of electrical energy in the prescribed manner.

The consumer of services cannot be limited in the consumption of electrical energy less than the power value established in the act of approval of emergency and technological armor, except for cases established by the legislation of the Russian Federation.

27. The provision of services for the transmission of electrical energy may be suspended by the network organization, subject to prior notification of this to the service consumer no later than 10 working days before the date of the expected suspension of the transmission of electrical energy.

The transmission of electrical energy is suspended by the network organization no later than 2 days from the date of the proposed introduction of the restriction specified in the notification of the administrator of the trading system (electricity supplier), also sent to the consumer of electrical energy.

If the circumstances that were the basis for the suspension of the transmission of electrical energy are eliminated before the expiration of the specified period, the suspension of the transmission of electrical energy is not carried out.

The transmission of electrical energy is resumed no later than 48 hours from the receipt of documentary evidence of the elimination of the circumstance that was the basis for the suspension of the transmission of electrical energy.

28. Termination of the contract, including upon expiration of its validity period, does not entail the disconnection of the power receiving device of the service consumer from the electrical network.

29. A break in the transmission of electrical energy, termination or restriction of the transmission of electrical energy is allowed by agreement of the parties, except in cases where the unsatisfactory condition of the energy receiving device (power installation) of the service consumer, certified by the authorized federal executive body for technological supervision, threatens an accident or poses a threat to life and security. The network organization is obliged to notify the service consumer about the interruption, termination or limitation of the transmission of electrical energy under these circumstances within 3 days from the date of such a decision, but no later than 24 hours before the introduction of these measures.

III. The procedure for accessing electrical networks in conditions of their limited capacity

30. When connecting to the electrical network and concluding an agreement, any consumer of services is assigned the right to receive electrical energy during any period of the agreement within the limits of the connected capacity determined by the agreement, the quality and parameters of which must comply with technical regulations and other mandatory requirements.

When accessing services for the transmission of electrical energy in conditions of limited capacity of electrical networks, the possibility of charging additional fees is excluded.

31. Restriction of the right to receive electrical energy is possible only in the event of a deviation from the normal operating modes of the electrical network caused by emergencies and (or) the removal of electrical power facilities for repairs or out of operation and leading to a power shortage.

At the same time, the limitation of electrical energy consumption is carried out in accordance with acts of approval of emergency and technological armor.

32. The capacity of the electrical network is determined according to the design scheme of the Unified Energy System of Russia, developed by the system operator together with the organization for managing the unified national (all-Russian) electrical network, taking into account the forecast balances of electrical energy and power. When carrying out such calculations, repair schedules for main generating equipment (agreed with generating companies), equipment for electrical substations and power lines, and power receiving equipment for electrical energy consumers with a controlled load are also taken into account.

The system operator and the organization for managing the unified national (all-Russian) electrical grid communicate to market participants information about the limitations of the capacity of the electrical network, including the results of these calculations.

IV. The procedure for setting tariffs for electric energy transmission services, providing for taking into account the degree of use of power of the electric network

33. Tariffs for services for the transmission of electrical energy are established taking into account the use by consumers of these services of the power of the electrical network to which they are directly technologically connected.

34. The consumer of services must notify the network organization at least 6 months before the next period of tariff regulation about the amount of declared capacity for the coming calendar year, which reflects the degree of use of power of the electrical network by the consumer of services.

The amount of declared power is determined for each point of connection and cannot exceed the maximum connected power at the corresponding point of connection to the network of this service consumer.

In the absence of the specified notification about the value of the declared power, when setting tariffs, the value of the maximum connected power of the power receiving device (power installation) of the service consumer is accepted.

When determining the basis for setting tariffs for the next regulation period, the grid organization has the right to use in relation to consumers of services that systematically exceed the amount of declared power, the amount of power declared by the consumer for the next regulation period or the actual amount of power used for the past period.

35. Tariffs for services for the transmission of electrical energy are established in accordance with the principles of pricing for electrical and thermal energy in the Russian Federation and the rules of state regulation and application of tariffs for electrical and thermal energy thermal energy in the Russian Federation, taking into account paragraph 34 of these Rules.

Taking into account the degree of power utilization of the electric network when determining the tariff for electric energy transmission services is carried out in accordance with the methodological instructions approved by the federal executive body on tariffs.

V. The procedure for determining losses in electrical networks and paying for these losses

36. Actual losses of electrical energy in electrical networks are defined as the difference between the volume of electrical energy supplied to the electrical network from other networks or from electricity producers, and the volume of electrical energy consumed by power receiving devices connected to this network, as well as transmitted to other networks organizations.

37. Grid organizations are obliged to compensate for actual losses of electrical energy that occurred in their network facilities, minus the losses included in the price of electrical energy.

38. Consumers of services, with the exception of producers of electrical energy, are required to pay, as part of the fee for services for the transmission of electrical energy, regulatory losses arising during the transmission of electrical energy through the network of a network organization with which the relevant persons have concluded an agreement, with the exception of losses included in the price (tariff) for electrical energy, in order to avoid double metering.

Consumers of services pay for losses of electrical energy in excess of the standard if it is proven that the losses arose through the fault of these consumers of services.

39. The amount of electrical energy losses in electrical networks, which is included in the fee for services for the transmission of electrical energy, is determined based on the standard for electrical energy losses. Loss standards are established by the authorized federal executive body in accordance with these Rules and the methodology for determining standard and actual losses of electrical energy in electrical networks.

40. Standards for losses of electrical energy in electrical networks are established in relation to the totality of power transmission lines and other electrical grid facilities belonging to the relevant network organization, taking into account differentiation by network voltage levels when setting tariffs for services for the transmission of electrical energy.

41. The methodology for determining standard and actual losses of electrical energy in electrical networks should provide for the calculation of losses based on:

technical characteristics of power lines and other power grid facilities that determine the amount of variable losses in accordance with the technology of transmission and conversion of electrical energy;

standard conditionally constant losses for power lines, power transformers and other power grid facilities;

standard losses in electrical energy measuring instruments.

When establishing standards, the technical condition of power lines and other power grid facilities may also be taken into account.

42. Network organizations purchase electrical energy in order to compensate for electrical energy losses in their networks:

on the wholesale electricity market;

if the grid organization is not a participant in the wholesale electricity market, - on the retail electricity market at the place of its activity.

VI. The procedure for provision and disclosure by network organizations of information on the capacity of electrical networks, their technical characteristics and the cost of services for the transmission of electrical energy

43. Information about the capacity of electrical networks and their technical characteristics is disclosed by the network organization in accordance with the standards for the disclosure of information by subjects of the wholesale and retail electricity markets.

44. The network organization discloses information on the technical characteristics of electrical networks quarterly no later than 30 working days from the end of the quarter.

45. The network organization is obliged to provide information on the availability of capacity of electrical networks and on the cost of services for the transmission of electrical energy upon request (in writing) of the service consumer.

46. ​​The requested information must be provided within 7 days from the date of receipt of the request with reimbursement by the service consumer of the costs of its provision actually incurred by the network organization.

47. Documents containing the requested information must be prepared in accordance with the established procedure by network organizations.

48. The grid organization is responsible for the timeliness, completeness and accuracy of the information provided and disclosed in the manner established by the legislation of the Russian Federation.

VII. The procedure for considering applications (complaints) regarding the provision of access to services for the transmission of electrical energy and making decisions on these applications (complaints) that are binding on legal entities and individuals

49. The basis for initiating and considering cases on issues of providing access to services for the transmission of electrical energy, making decisions and issuing orders by the antimonopoly authority are statements of the authorities state power or statements (complaints) of legal entities and individuals.

50. The application (complaint) must contain information about the applicant and the person against whom the application (complaint) was filed, a description of the violation of the requirements of these Rules, as well as the demands that the applicant is making.

51. The antimonopoly authority considers the application (complaint) within a month from the date of its receipt.

In case of insufficiency or absence of evidence allowing one to come to a conclusion about the presence or absence of signs of violation of the requirements of these Rules, the antimonopoly authority has the right to collect and analyze additional evidence to extend the period for consideration of the application (complaint) to 3 months from the date of its receipt. The antimonopoly authority is obliged to notify the applicant in writing about the extension of the period for consideration of the application (complaint).

52. If there are no signs of violation of the requirements of these Rules and antimonopoly legislation, the antimonopoly authority notifies the applicant in writing within 10 days from the date of the decision.

53. Cases of violations of antimonopoly legislation are considered by the antimonopoly authority in accordance with the legislation of the Russian Federation.

54. The consideration of cases of violations of the requirements of these Rules in terms of providing access to services for the transmission of electrical energy and antimonopoly legislation and the adoption of decisions (instructions) on them are carried out in the manner established by the federal antimonopoly body.

55. Federal executive authorities, executive authorities of constituent entities of the Russian Federation, local government bodies, other bodies or organizations (their officials) vested with the functions or rights of these authorities, commercial and non-profit organizations(their managers), individuals, including individual entrepreneurs, has the right to appeal decisions and orders in whole or in part of the antimonopoly authority in the manner established by the legislation of the Russian Federation.

Rules for non-discriminatory access to services for operational dispatch control in the electric power industry and the provision of these services

1. These Rules define the general principles and procedure for ensuring non-discriminatory access of subjects of the electric power industry (hereinafter - consumers of services) to services for operational dispatch control in the electric power industry (hereinafter - services) provided by the system operator and other subjects of operational dispatch control (hereinafter - system operator ), as well as the procedure for providing these services.

2. These Rules do not apply to relations related to the provision of services by subordinate subjects of operational dispatch control in the electric power industry to higher-level subjects of operational dispatch control in the electric power industry.

3. Non-discriminatory access to services involves ensuring equal conditions for the provision of services to their consumers, regardless of their organizational and legal form and legal relations with the person providing these services.

4. The system operator is obliged to disclose information regarding access to services and the provision of services in accordance with the standards for disclosure of information by subjects of the wholesale and retail electricity markets.

5. The system operator provides the following services:

a) management of technological operating modes of electric power facilities;

b) medium- and long-term forecasting of the volume of production and consumption of electrical energy;

c) participation in the formation of a reserve of production energy capacities;

d) approval of the removal for repair and decommissioning of electrical grid facilities and energy facilities for the production of electrical and thermal energy, as well as their commissioning after repair;

e) development of daily operating schedules for power plants and electrical networks of the Unified Energy System of Russia;

f) frequency regulation electric current, ensuring the functioning of the automatic control system for the frequency of electric current and power, ensuring the functioning of system and emergency automation;

g) organization and management of parallel operation modes of the Unified Energy System of Russia and electric power systems of foreign countries;

h) participation in the formation and issuance of technological requirements for technological connection of electric power industry entities to the unified national (all-Russian) electric grid and territorial distribution networks, ensuring their operation as part of the Unified Energy System of Russia.

6. Services are provided on the basis of a bilateral agreement on the provision of services for operational dispatch control in the electric power industry (hereinafter referred to as the agreement), as well as on the basis of an agreement on joining the trading system of the wholesale electricity market.

7. The consumer of services can simultaneously be a participant in the contracts specified in paragraph 6 of these Rules only under the following conditions:

the provisions of these agreements regarding the provision of services are completely identical;

the total cost of services provided on the basis of these contracts is determined by the tariffs established by the federal executive body on tariffs.

8. The conclusion of an agreement between the service consumer and the system operator is mandatory for both parties.

9. Wholesale market entities enter into an agreement with the system operator before they enter into an agreement with the organization managing the unified national (all-Russian) electrical network for the provision of services for the transmission of electrical energy through the unified national (all-Russian) electrical network.

10. The price of services is determined by the tariffs established by the federal executive body on tariffs.

11. The consumer of services who intends to conclude an agreement (hereinafter referred to as the applicant) sends to the system operator an application in writing for access to services, which must contain the following information:

details of the service consumer;

points of connection to networks of a network organization;

start dates for services.

The applicant, along with the application, has the right to send the system operator a draft agreement.

12. The system operator, within 30 days from the date of receipt of the application for access to services, is obliged to consider it and make a decision on providing access to services or refusing it.

13. In the absence of the information specified in paragraph 11 of these Rules, the system operator notifies the applicant about this within 3 days and, within 30 days from the date of receipt of the missing information, considers the application for access to services in accordance with paragraph 12 of these Rules.

14. If a decision is made to provide access to services, the system operator is obliged to send the applicant a signed draft agreement.

15. The applicant, who has received a signed draft agreement from the system operator and has no objections to its terms, fills out the agreement in the part related to information about the applicant and sends 1 signed copy of the agreement to the system operator.

16. If the applicant has submitted a draft agreement, and the system operator has no objections to its terms, the latter is obliged to sign it and send 1 signed copy of the agreement to the applicant.

The agreement is considered concluded from the date of its signing by both parties, unless otherwise established by this agreement or a court decision.

17. If a decision is made to refuse to provide access to services, the system operator is obliged to send the applicant a notice in writing and documents justifying the refusal no later than 10 days from the date of receipt of the application specified in paragraph 11 of these Rules.

A refusal to provide access to services may be appealed to the antimonopoly authority and (or) challenged in court.

18. The system operator has the right to refuse to provide access to services in the following cases:

a) the applicant did not provide the information provided for in paragraph 11 of these Rules;

b) the applicant provided false information;

c) the applicant’s energy facilities are located outside the area of ​​his dispatch responsibility.

In this case, the applicant has the right to re-apply to the system operator with an application for access to services. If the grounds for refusal are eliminated, the system operator does not have the right to refuse to provide the applicant with access to services.

19. The provision of services is carried out in order to ensure reliable energy supply and quality of electrical energy that meets the requirements of technical regulations and other mandatory requirements established by regulatory legal acts, and to take measures to ensure the fulfillment of obligations of electricity industry entities under contracts concluded on the wholesale and retail markets of electrical energy.

As part of the provision of services, the system operator is obliged to choose the most economically effective solution, which ensures the safe and trouble-free operation of the technological infrastructure of the electric power industry and the quality of electrical energy that meets the requirements of technical regulations and other mandatory requirements.

20. Consumers of services have the right not to execute operational dispatch commands and orders if their execution poses a threat to human life, the safety of equipment or leads to a violation of the limits and conditions for the safe operation of nuclear power plants.

21. In the event of emergency electrical power conditions, the provision of services is carried out taking into account the specifics established by the legislation of the Russian Federation.

Rules for non-discriminatory access to the services of the administrator of the wholesale market trading system and the provision of these services

1. These Rules define the general principles and procedure for ensuring non-discriminatory access of subjects of the wholesale electricity (capacity) market (hereinafter - subjects of the wholesale market) to services for organizing the functioning of the trading system of the wholesale market of electricity (capacity), organization wholesale trade electrical energy and reconciliation and offset of mutual counter obligations of trading participants (hereinafter referred to as the services) of the administrator of the wholesale market trading system (hereinafter referred to as the administrator), as well as the procedure for providing these services.

2. Non-discriminatory access to administrator services provides for equal conditions for the provision of services to subjects of the wholesale market, regardless of their organizational and legal form and legal relations with the person providing these services.

3. The administrator is obliged to disclose information regarding access to services and their provision in accordance with the standards for disclosure of information by subjects of the wholesale and retail electricity markets.

4. The administrator does not have the right to refuse to provide services to subjects of the wholesale market, except for the cases established by these Rules and the rules of the wholesale electricity market.

5. Administrator services can be provided to the following persons:

included in the list commercial organizations- subjects of the federal (all-Russian) wholesale electricity (capacity) market, electricity tariffs for which are established by the federal executive body on tariffs, before the rules of the wholesale electricity market come into force;

having received the status of a wholesale market entity in accordance with the rules of the wholesale electricity market by providing the administrator with the documents and information specified in these Rules, and the wholesale market entities signing an agreement on joining the trading system of the wholesale electricity (capacity) market.

6. A legal entity wishing to gain access to the services of an administrator (hereinafter referred to as the applicant) must submit an application for this and submit the following documents to the administrator:

information about the type of wholesale market entity (generating company, energy sales organization, energy supply organization, supplier of last resort, electricity consumer, etc.) to which the applicant corresponds, in accordance with the rules of the wholesale electricity (capacity) market of the transition period;

signed authorized person the applicant 5 copies of the draft agreement on joining the trading system of the wholesale electricity (power) market in the form approved by the administrator;

the applicant's application form in the prescribed form;

notarized copies of constituent documents;

notarized copy of the certificate of state registration legal entity;

a notarized copy of the certificate of registration of the applicant with tax authorities Russian Federation;

documents confirming the powers of persons representing the interests of the applicant;

a document confirming the assignment of the organization to the status of a guaranteeing supplier in cases and in the manner established by the legislation of the Russian Federation;

a single-line diagram of connection to an external electrical network, agreed upon with the owner or other legal owner of the network facilities to which the applicant or third parties whose interests he represents are technologically connected, indicating the names and voltage levels of the buses of external substations, proposed groups of delivery points, and places of connection of devices commercial metering, voltage measuring transformers and balance sheet boundaries certified by representatives of adjacent owners of electrical networks;

acts of delimitation of balance sheet ownership and operational responsibility, agreed upon with the owners or other legal owners of network facilities to which the applicant or third parties whose interests the applicant intends to represent are technologically connected.

An applicant who has the right to purchase and sell electrical energy (power) in the regulated sector is required to submit to the administrator a document confirming the inclusion of the legal entity in the list of commercial organizations - subjects of the federal (all-Russian) wholesale electrical energy (capacity) market, the tariffs for electrical energy for which are established by the federal executive body on tariffs.

In order to confirm the compliance of generating and power receiving equipment quantitative characteristics, presented to objects participating in the wholesale electricity market, the applicant submits passport documents to the administrator technological characteristics the specified equipment.

7. An applicant representing the interests of third parties in the wholesale electricity (capacity) market provides the administrator with information on the technological characteristics of the generating equipment of the suppliers whose interests he represents, and (or) the technological characteristics of the energy receiving equipment of the consumers whose interests he represents.

An applicant carrying out activities in the transmission of electrical energy and purchasing electrical energy on the wholesale electrical energy (power) market, in order to compensate for losses in electrical networks, submits to the administrator the characteristics of the electrical network and network facilities for each group of supply points (network facility).

In order to obtain data on actual energy production and consumption, as well as to carry out calculations on the wholesale electricity (power) market, the applicant submits documents indicating compliance of the commercial accounting system with mandatory technical requirements and the terms of the agreement on joining the trading system of the wholesale electricity (capacity) market, in the manner determined by the administrator.

All documents must be submitted by the applicant in accordance with the requirements determined by the administrator.

The administrator has no right to demand the provision of information not provided for by these Rules, unless otherwise established by the legislation of the Russian Federation.

In order to ensure equal access to the administrator’s services, the owner or other legal owner of network facilities to which the applicant or third parties whose interests he represents is technologically connected is obliged to ensure approval of a single-line connection diagram to the external electrical network and draw up acts of delimitation of balance sheet responsibility.

8. The administrator has the right to refuse access to the administrator’s services if the applicant:

a) did not submit the documents and information provided for in paragraph 6 of these Rules;

b) provided false information;

c) does not comply with any of the requirements established by the legislation of the Russian Federation for subjects of the wholesale market.

The applicant has the right to re-apply to the administrator for access to the administrator’s services if the grounds for denying the applicant access to the administrator’s services are eliminated.

9. The decision to deny access to the administrator’s services may be appealed in the manner established by the legislation of the Russian Federation.

10. The administrator provides services to subjects of the wholesale market on the basis of an agreement on joining the trading system of the wholesale electricity market.

A signed copy of the agreement on joining the trading system of the wholesale electricity (power) market is sent by the administrator to the wholesale market entity.

11. Administrator services are paid by the wholesale market entity at tariffs approved by the federal executive body for tariffs.

12. In the event of non-payment of administrator services by a wholesale market entity, the administrator has the right to suspend the acceptance of applications from a wholesale market entity to participate in the procedure for competitive selection of price applications in the free trade sector of the wholesale market until the debt is fully repaid.

13. The administrator has the right to stop providing services to a wholesale market entity in the event of:

non-compliance of a legal entity with the requirements for a wholesale market entity;

loss of the status of a wholesale market entity by a legal entity;

repeated failure or improper fulfillment by a wholesale market entity of obligations to pay for administrator services;

termination of the agreement on joining the wholesale market trading system;

termination of the activities of a wholesale market entity on the grounds provided for by the legislation of the Russian Federation.

14. The adoption by the administrator, in accordance with the rules of the wholesale electricity (power) market of the transition period and the agreement on joining the trading system of the wholesale electricity market, of a decision to recognize the sale (purchase) of electricity in the free trade sector in general or in any limited territory failed cannot be considered as non-fulfillment or improper fulfillment of obligations to provide administrator services.

Rules for technological connection of power receiving devices (power installations) of legal entities and individuals to electrical networks

I. General provisions

1. These Rules determine the procedure for technological connection of energy receiving devices (power installations) of legal entities and individuals (hereinafter referred to as energy receiving devices), regulate the procedure for technological connection, determine the essential terms of the agreement on the implementation of technological connection to electrical networks (hereinafter referred to as the agreement), establish requirements for issuance of individual technical conditions for connection to electrical networks (hereinafter referred to as technical conditions) and criteria for the presence (absence) of the technical possibility of technological connection.

2. These Rules apply to persons whose power receiving devices were previously connected to the electrical network and who declared the need to review (increase) the amount of connected power.

3. The grid organization is obliged to carry out, in relation to any person who contacts it, measures for the technological connection of newly commissioned, newly built, expanding their previously connected capacity and reconstructed power receiving devices to their electrical networks (hereinafter referred to as technological connection), subject to their compliance with these Rules and the availability of technical capabilities for technological connection.

In relation to power receiving devices technologically connected to the electrical network before the entry into force of these Rules, the contract is not concluded and the measures specified in paragraph 12 of these Rules are not carried out.

4. Any persons have the right to technological connection of power transmission lines they have built to electrical networks in accordance with these Rules.

5. When connecting power plants to the distribution devices of a power plant, the latter performs the functions of a network organization in terms of carrying out activities under the contract.

6. Technological connection is carried out on the basis of an agreement concluded with the grid organization within the time limits established by these Rules. The conclusion of an agreement is mandatory for a network organization. In the event of an unjustified refusal or evasion by a network organization from concluding a contract, the interested party has the right to file a claim in court to compel the conclusion of the contract and to recover damages caused by such an unjustified refusal or evasion.

7. These Rules establish the following procedure for technological connection:

filing an application for technological connection with a requirement to issue technical specifications;

preparation of technical specifications and submission of a draft agreement including technical specifications;

conclusion of an agreement;

compliance with technical conditions on the part of the connected person and on the part of the network organization;

performing actions to connect and ensure operation of the power receiving device in the electrical network;

checking compliance with technical conditions and drawing up an act on technological connection.

II. The procedure for concluding and fulfilling the contract

8. To obtain technical conditions and carry out technological connection, the person who owns the power receiving device sends an application for technological connection (hereinafter referred to as the application) to the network organization to whose electrical network the technological connection is planned.

9. The application must include the following information:

a) full name of the applicant;

b) location of the applicant;

c) the postal address of the applicant;

d) a plan for the location of the power receiving device in relation to which it is planned to carry out measures for technological connection;

e) maximum power of the energy receiving device and its specifications, number, power of generators and transformers connected to the network;

f) the number of points of connection to the electrical network, indicating the technical parameters of the elements of electrical installations connected at specific points of the electrical network;

g) a single-line diagram of the applicant’s electrical networks connected to the networks of the grid organization, indicating the possibility of redundancy from its own energy supply sources (including redundancy of its own needs) and the possibility of switching loads (generation) through the applicant’s internal networks;

h) the declared level of reliability of the power receiving device;

i) the nature of the load of the electrical energy consumer (for generators - the possible speed of increasing or decreasing the load) and the presence of loads that distort the shape of the electric current curve and cause voltage asymmetry at connection points;

j) the value and justification of the value of the technological minimum (for generators) and emergency armor (for consumers of electrical energy);

k) permission from the authorized state supervision body to allow the power receiving device into operation (except for facilities under construction);

l) the scope of possible participation in automatic or operational emergency power control (for power plants and consumers, with the exception of individuals) in the provision of services in accordance with a separate agreement;

m) the scope of possible participation in normalized primary frequency regulation and secondary power regulation (for power plants) in the provision of services in accordance with a separate agreement;

o) list and capacity of consumer's current collectors (except for individuals), which can be turned off using an emergency automatic device.

The list of information provided in the application is exhaustive.

The grid organization has no right to demand the provision of information not provided for by these Rules.

10. The grid organization is obliged to send a draft agreement to the applicant for approval within 30 days from the date of receipt of the application.

If the information specified in paragraph 9 of these Rules is missing, or is provided incompletely, the network organization notifies the applicant within 6 working days and considers the application within 30 days from the date of receipt of the missing information.

When especially complex nature technological connection of power receiving devices for the organization managing the unified national (all-Russian) electrical network or other owners of such network facilities, the specified period by agreement of the parties can be increased to 90 days. The applicant is notified of the increase in the period and the reasons for its change.

11. The contract must contain the following essential terms:

measures for technological connection and obligations of the parties to implement them;

fulfillment of technical conditions;

deadlines for the grid organization to carry out technological connection activities;

the amount of fees for carrying out technological connection activities;

responsibility of the parties for fulfilling the terms of the agreement;

boundaries of delineation of balance sheet ownership.

12. Activities for technological connection include:

a) development of a power supply scheme;

b) technical inspection (inspection) of connected power receiving devices by an authorized government body with the participation of representatives of the network organization;

c) preparation and issuance of technical specifications;

d) compliance with technical conditions (on the part of the person whose energy-receiving device is connected, and on the part of the network organization);

e) actual actions to connect and ensure operation of the power receiving device in the electrical network;

f) checking compliance with technical conditions and drawing up an act on technological connection.

The list of activities for technological connection is exhaustive.

It is prohibited to impose services not provided for by these Rules on a person interested in technological connection.

13. The network organization is obliged, within 30 days from the date of receipt of the application, to consider it, prepare technical conditions for technological connection and agree on them with the system operator (subject of operational dispatch control), and the organization for managing the unified national (all-Russian) electrical network or other owners objects of such a network in the cases provided for in paragraph three of clause 10 of these Rules - within 90 days.
The grid organization is obliged, within 5 days from the date of receipt of the application, to send a copy of it for consideration by the system operator (subject of operational dispatch control), and then, together with him, review it and prepare technical conditions for technological connection.
14. Technical conditions for technological connection are an integral part of the contract.
IN technical conditions must be indicated:
a) circuits for issuing or receiving power and points of connection to the electrical network (power lines or base substations);
b) justified requirements for strengthening the existing electrical network in connection with the connection of new capacities (construction of new power lines, substations, increasing the cross-section of wires and cables, increasing the capacity of transformers, expanding distribution devices, installing compensating devices to ensure the quality of electricity);
c) calculated values ​​of short circuit currents, requirements for relay protection, voltage regulation, emergency automation, telemechanics, communications, insulation and overvoltage protection, as well as for electrical energy and power metering devices in accordance with the requirements established by regulatory legal acts;
d) requirements for equipping power plants with emergency automatic equipment for issuing power and for equipping consumers with emergency automatic devices;
e) requirements for equipping with devices that ensure the participation of power plants or consumers in automatic or operational emergency power control in the provision of services in accordance with a separate contract;
f) requirements for equipping with devices that ensure the participation of power plants in normalized primary frequency regulation and in secondary power regulation in the provision of services in accordance with a separate contract.
III. Criteria for the presence (absence) of technical possibility of technological connection
15. The criteria for the availability of technical possibility of technological connection are:
a) the location of the power receiving device, in respect of which an application for technological connection has been submitted, within the territorial boundaries of service of the corresponding network organization;
b) no restrictions on connected power in the network node to which the technological connection is to be made.
If any of the specified criteria is not met, there is no technical possibility of technological connection.
In order to verify the validity of the network organization’s determination of the lack of technical feasibility, the applicant has the right to apply to the authorized federal executive body for technological supervision to obtain an opinion on the presence (absence) of the technical possibility of technological connection by the network organization.
16. Restrictions on the connection of additional power arise if the full use of the consumed (generating) power of all previously connected consumers of services for the transmission of electrical energy and the power of the newly connected power receiving device can lead to the load of the energy equipment of the network organization exceeding the values ​​​​defined by technical standards and standards approved or adopted in the manner established by the legislation of the Russian Federation.
17. If there is a restriction on connecting new power, it is allowed to connect power receiving devices to electrical networks within the power value that does not cause restrictions on the use of consumed (generating) power of all electrical energy consumers previously connected to a given network node, or in the declared volume in agreement with the specified consumers.

It does not work Editorial from 27.12.2004

Name of documentDecree of the Government of the Russian Federation of December 27, 2004 N 861 "ON APPROVAL OF THE RULES FOR NON-DISCRIMINATORY ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATORY ACCESS TO OPERATIONAL DISPATCHER SERVICES WHO IS MANAGED IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE TRADE ADMINISTRATOR WHOLESALE MARKET SYSTEMS AND PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEPTION DEVICES (POWER INSTALLATIONS) OF LEGAL AND INDIVIDUALS TO ELECTRIC NETWORKS"
Document typedecree, rules
Receiving authorityRussian government
Document Number861
Acceptance date04.01.2005
Revision date27.12.2004
Date of registration with the Ministry of Justice01.01.1970
StatusIt does not work
Publication
  • Document in electronic form FAPSI, STC "System"
  • "Rossiyskaya Gazeta", N 7, 01/19/2005
  • "Collection of Legislation of the Russian Federation", N 52, 12/27/2004, part 2, article 5525
NavigatorNotes

Decree of the Government of the Russian Federation of December 27, 2004 N 861 "ON APPROVAL OF THE RULES FOR NON-DISCRIMINATORY ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATORY ACCESS TO OPERATIONAL DISPATCHER SERVICES WHO IS MANAGED IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE TRADE ADMINISTRATOR WHOLESALE MARKET SYSTEMS AND PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEPTION DEVICES (POWER INSTALLATIONS) OF LEGAL AND INDIVIDUALS TO ELECTRIC NETWORKS"

Resolution

In order to promote the development of competition in the market for the production and sale of electrical energy, to protect the rights of consumers of electrical energy and in accordance with articles , , and the Federal Law "On Electric Power Industry", the Government of the Russian Federation decides:

1. Approve the attached:

Rules for non-discriminatory access to electric energy transmission services and the provision of these services;

Rules for non-discriminatory access to services for operational dispatch control in the electric power industry and the provision of these services;

Rules for non-discriminatory access to the services of the administrator of the wholesale market trading system and the provision of these services;

Rules for the technological connection of energy receiving devices (power installations) of legal entities and individuals to electrical networks.

2. Designate the Federal Antimonopoly Service as the authorized federal executive body to ensure state control over compliance with the rules of non-discriminatory access to electric energy transmission services, operational dispatch management services in the electric power industry and trading system administrator services.

3. The Ministry of Industry and Energy of the Russian Federation, within 3 months, develop and approve a methodology for determining standard and actual losses of electrical energy in electrical networks.

Chairman of the Government
Russian Federation
M.FRADKOV

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

RULES OF NON-DISCRIMINATIONAL ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND PROVISION OF THESE SERVICES I. General provisions

1. These Rules define the general principles and procedure for ensuring non-discriminatory access to electric energy transmission services, as well as the provision of these services.

2. The terms used in these Rules mean the following:

“territorial distribution network” - a complex of power lines and equipment not included in the unified national (all-Russian) electrical network used to provide services for the transmission of electrical energy;

“grid organizations” - commercial organizations whose main activity is the provision of services for the transmission of electrical energy through electrical networks, as well as the implementation of technological connection activities;

“point of connection to the electrical network” - the place of physical connection of the power receiving device (power installation) (hereinafter referred to as the power receiving device) of the consumer of electric energy transmission services (hereinafter referred to as the consumer of services) with the electrical network of the network organization;

“electric network throughput” is the technologically maximum permissible value of power that can be transmitted taking into account operating conditions and reliability parameters of the functioning of electric power systems;

“balance sheet boundary” is the line of dividing electric grid facilities between owners on the basis of ownership or possession on another legal basis.

Other concepts used in these Rules correspond to the concepts defined by the legislation of the Russian Federation.

3. Non-discriminatory access to electric energy transmission services involves ensuring equal conditions for the provision of these services to their consumers, regardless of the organizational and legal form and legal relations with the person providing these services.

4. Grid organizations are required to disclose information regarding access to electric energy transmission services and the provision of these services in accordance with the standards for information disclosure by subjects of the wholesale and retail electric energy markets.

5. These Rules do not apply to relations related to the provision of intersystem electrical connections, unless otherwise provided by the legislation of the Russian Federation.

6. Services for the transmission of electrical energy are provided by the network organization on the basis of an agreement on the paid provision of services for the transmission of electrical energy to persons who, by right of ownership or on another legal basis, have power receiving devices and other electric power facilities technologically connected in the prescribed manner to the electrical network, as well as subjects of the wholesale electricity market exporting (importing) electricity, energy sales organizations and guaranteeing suppliers.

7. The grid organization, in fulfillment of its obligations to consumers of services under the contract for the provision of services for the transmission of electrical energy (hereinafter referred to as the contract), is obliged to regulate relations for the provision of intersystem electrical connections with other grid organizations that have technological connections to electrical networks owned or controlled by on another legal basis for this network organization, in the manner prescribed by the legislation of the Russian Federation.

8. During the transition period of operation of the electric power industry, the provision of services for the transmission of electrical energy using facilities included in the unified national (all-Russian) electrical network is carried out on the basis of an agreement concluded both on behalf of the organization for managing the unified national (all-Russian) electrical network, and from on behalf of other owners of these objects.

II. The procedure for concluding and executing an agreement

9. The agreement is public and mandatory for the network organization.

Unreasonable evasion or refusal by a network organization to conclude an agreement may be appealed by the consumer of services in the manner established by the legislation of the Russian Federation.

10. An agreement cannot be concluded before the conclusion of an agreement on the technological connection of energy receiving devices (power installations) of legal entities and individuals to electrical networks, except for cases where the consumer of services is:

a person whose power receiving device was technologically connected to the electrical network before these Rules came into force;

a person who exports (imports) electrical energy and does not own, use or dispose of electrical power facilities connected to the electrical network;

an energy sales organization (supplier of last resort) that enters into an agreement in the interests of the consumers of electrical energy it serves.

In relation to these persons, the network organization has the right, in order to determine the technical characteristics of power receiving devices (power installations) necessary for the provision of services for the transmission of electrical energy, to request information and documentation necessary for technological connection.

11. Under the contract, the network organization undertakes to carry out a set of organizationally and technologically related actions that ensure the transmission of electrical energy through technical devices of electrical networks, and the consumer of services - to pay for them.

12. The contract must contain the following essential terms:

the maximum power value of the power receiving device connected to the electrical network, with the distribution of the specified value for each connection point of the electrical network in respect of which technological connection was carried out in the manner established by the legislation of the Russian Federation;

the amount of power (generating or consumed) within which the network organization undertakes to ensure the transmission of electrical energy at the connection points specified in the contract;

responsibility of the service consumer and the network organization for the condition and maintenance of electric grid facilities, which is determined by their balance sheet and is recorded in the act of delimitation of the balance sheet of electric grids and the operational responsibilities of the parties attached to the contract;

the amount of technological and emergency reservation (for consumers - legal entities or entrepreneurs without forming a legal entity who meet the relevant requirements established by the legislation of the Russian Federation in the field of electric power industry), which must be taken into account when determining the procedure for limiting the power consumption regime. For these persons, the act of approval of emergency and technological armor is a mandatory annex to the contract;

obligations of the parties to equip connection points with means of measuring electrical energy, including measuring instruments that comply with the requirements established by the legislation of the Russian Federation, as well as ensuring their operability and compliance during the entire term of the contract with operational requirements for them established by the authorized body for technical regulation and metrology and the manufacturer.

13. The service consumer assumes the following obligations in accordance with the contract:

pay the network organization for services for the transmission of electrical energy within the terms and amounts established by the contract;

maintain the relay protection and emergency automation equipment, electricity and power metering devices, as well as other devices necessary to maintain the required parameters of reliability and quality of electricity, which are in his possession or on another legal basis, and comply with the requirements during the entire term of the contract , established for technological connection and in the operating rules of the specified means, instruments and devices;

submit to the network organization, within the time limits established by the contract, the necessary technological information: main electrical diagrams, equipment characteristics, diagrams of relay protection devices and emergency automation, operational data on the technological operating modes of the equipment;

inform the network organization within the time limits established by the contract about emergencies at energy facilities, planned, current and major repairs at them;

inform the network organization about the scope of participation in automatic or operational emergency power control, in normalized primary frequency regulation and in secondary power regulation (for power plants), as well as about the list and power of the service consumer's current collectors that can be turned off by emergency automatic devices;

fulfill obligations to ensure the safe operation of energy networks under their control and the serviceability of the instruments and equipment they use related to the transmission of electrical energy;

freely admit authorized representatives of the grid organization to the points of control and recording of the quantity and quality of transferred electrical energy in the manner established by the agreement.

14. The grid organization assumes the following obligations in accordance with the agreement:

ensure the transfer of electrical energy to the energy receiving devices of the service consumer, the quality and parameters of which must comply with technical regulations and other mandatory requirements;

carry out the transfer of electrical energy in accordance with the agreed reliability parameters, taking into account the technological characteristics of power receiving devices (power plants);

in the manner and within the time limits established by the contract, inform the service consumer about emergencies in electrical networks, repair and maintenance work that affect the fulfillment of obligations under the contract;

freely admit authorized representatives of service consumers to points of control and recording of the quantity and quality of transferred electrical energy in the manner established by the contract.

15. A person who intends to conclude an agreement (hereinafter referred to as the applicant) sends a written application to the network organization to conclude an agreement, which must contain the following information:

details of the consumer of electric energy transmission services; volumes and expected mode of transmission of electrical energy broken down by month;

the volume of maximum power and the nature of the load of energy receiving devices (power plants) connected to the network (generating or consumed), with its distribution at each point of connection of the electrical network and indicating the boundaries of the balance sheet;

single-line diagram of the electrical network of a service consumer connected to the networks of a network organization;

points of connection to the networks of the network organization, indicating for each point of connection to the network the declared power values, including the power values ​​during the period of maximum loads of electrical energy consumers;

start date for the provision of electricity transmission services;

reference to the agreement on the provision of services for operational dispatch control (in the case of concluding an agreement on the provision of services for the transmission of electrical energy with an organization for managing the unified national (all-Russian) electrical grid).

16. The network organization, within 30 days from the date of receipt of the application for concluding an agreement, is obliged to consider it and send the applicant a draft agreement signed by the network organization or a reasoned refusal to conclude it.

17. In the absence of information specified in paragraph 15 of these Rules, the network organization notifies the applicant about this within 6 working days and, within 30 days from the date of receipt of the missing information, considers the application in accordance with paragraph 16 of these Rules.

18. The applicant, who has received a draft agreement from the network organization, fills it out in the part related to the information about the applicant included in the agreement, and sends one signed copy of the agreement to the network organization.

19. The agreement is considered concluded from the date it is signed by the applicant, unless otherwise established by the agreement or court decision.

20. The grid organization has the right to refuse to conclude an agreement in the event of:

the consumer of services does not have a concluded agreement on the provision of services for operational dispatch control (in the case of concluding an agreement on the provision of services for the transmission of electrical energy with an organization for managing the unified national (all-Russian) electrical grid);

lack of technical capability to provide services for the transmission of electrical energy in the declared volume (if the volume of power is declared, the proper transmission of which cannot be ensured by the grid organization based on the existing conditions of technological connection);

sending an application to conclude an agreement by a person who does not have a technological connection to the electrical networks of this network organization. At the same time, a mandatory condition for concluding an agreement with guaranteeing suppliers and energy sales organizations is the presence of a technological connection of consumers of electrical energy in whose favor the agreement is concluded, and for organizations engaged in the export-import of electrical energy, the presence of a connection between the electrical networks of this network organization and the electrical networks neighboring states through whose territories export and import supplies of electrical energy are carried out.

21. If it is not technically possible to provide services for the transmission of electrical energy within the scope of services declared by the consumer, the network organization is obliged to notify the applicant within 30 days about the conditions and to what extent the service can be provided and the contract can be concluded.

22. If there are grounds for refusal to conclude an agreement, the network organization is obliged, no later than 30 days from the date of receipt of the application specified in paragraph 15 of these Rules, to send to the applicant in writing a reasoned refusal to conclude an agreement with supporting documents attached.

Refusal to conclude an agreement may be challenged in the manner established by the legislation of the Russian Federation.

23. A prerequisite for the provision of services for the transmission of electric energy to the consumer of services is that he has the status of a participant in the wholesale market or has concluded an electric energy purchase and sale agreement with a guarantee supplier, energy sales organization or other supplier of electric energy.

24. The grid organization has the right to suspend the transmission of electrical energy in the following cases:

the occurrence of debt of the consumer of services to pay for electric energy transmission services for 2 or more billing periods;

violation by the consumer of the terms of payment for services for the transmission of electrical energy, defined in the purchase and sale agreement concluded by him (agreement on accession to the wholesale electricity (capacity) market), - in the presence of appropriate notification in writing from the administrator of the trading system, the guaranteeing supplier or the energy sales organization with the attachment of supporting documents indicating the amount of the consumer’s debt confirmed by a reconciliation act or a court decision, the deadline for its repayment, as well as the expected period for introducing restrictions on the consumption regime;

connection by the consumer of services to the electrical network of power receiving devices (power installations) that do not comply with the terms of the contract, or connection carried out in violation of the procedure for technological connection of power receiving devices of legal entities and individuals to electrical networks.

25. The transmission of electrical energy is suspended in the event of:

absence or expiration of the obligation of the supplier (seller) of electrical energy to the consumer under the supply agreement (purchase and sale, energy supply, etc.) of electrical energy (power), which must be transmitted through the networks of the network organization;

termination of the participation of the service consumer in the wholesale market, of which the network organization must be notified in writing by the electricity supplier or the administrator of the trading system, indicating the grounds, at least 10 days before the date of termination of these obligations. Such notification is sent to the consumer at the same time.

26. Suspension of the transmission of electrical energy does not entail termination of the contract.

When the transmission of electrical energy is suspended on the grounds provided for in paragraph 24 of these Rules, consumers of services are allowed to partially or completely limit the mode of consumption of electrical energy in the prescribed manner.

The consumer of services cannot be limited in the consumption of electrical energy less than the power value established in the act of approval of emergency and technological armor, except for cases established by the legislation of the Russian Federation.

27. The provision of services for the transmission of electrical energy may be suspended by the network organization, subject to prior notification of this to the service consumer no later than 10 working days before the date of the expected suspension of the transmission of electrical energy.

The transmission of electrical energy is suspended by the network organization no later than 2 days from the date of the proposed introduction of the restriction specified in the notification of the administrator of the trading system (electricity supplier), also sent to the consumer of electrical energy.

If the circumstances that were the basis for the suspension of the transmission of electrical energy are eliminated before the expiration of the specified period, the suspension of the transmission of electrical energy is not carried out.

The transmission of electrical energy is resumed no later than 48 hours from the receipt of documentary evidence of the elimination of the circumstance that was the basis for the suspension of the transmission of electrical energy.

28. Termination of the contract, including upon expiration of its validity period, does not entail the disconnection of the power receiving device of the service consumer from the electrical network.

29. A break in the transmission of electrical energy, termination or restriction of the transmission of electrical energy is allowed by agreement of the parties, except in cases where the unsatisfactory condition of the energy receiving device (power installation) of the service consumer, certified by the authorized federal executive body for technological supervision, threatens an accident or poses a threat to life and security. The network organization is obliged to notify the service consumer about the interruption, termination or limitation of the transmission of electrical energy under these circumstances within 3 days from the date of such a decision, but no later than 24 hours before the introduction of these measures.

III. The procedure for accessing electrical networks in conditions of their limited capacity

30. When connecting to the electrical network and concluding an agreement, any consumer of services is assigned the right to receive electrical energy during any period of the agreement within the limits of the connected capacity determined by the agreement, the quality and parameters of which must comply with technical regulations and other mandatory requirements.

When accessing services for the transmission of electrical energy in conditions of limited capacity of electrical networks, the possibility of charging additional fees is excluded.

31. Restriction of the right to receive electrical energy is possible only in the event of a deviation from the normal operating modes of the electrical network caused by emergencies and (or) the removal of electrical power facilities for repairs or out of operation and leading to a power shortage.

At the same time, the limitation of electrical energy consumption is carried out in accordance with acts of approval of emergency and technological armor.

32. The capacity of the electrical network is determined according to the design scheme of the Unified Energy System of Russia, developed by the system operator together with the organization for managing the unified national (all-Russian) electrical network, taking into account the forecast balances of electrical energy and power. When carrying out such calculations, repair schedules for main generating equipment (agreed with generating companies), equipment for electrical substations and power lines, and power receiving equipment for electrical energy consumers with a controlled load are also taken into account.

The system operator and the organization for managing the unified national (all-Russian) electrical grid communicate to market participants information about the limitations of the capacity of the electrical network, including the results of these calculations.

IV. The procedure for setting tariffs for electric energy transmission services, providing for taking into account the degree of use of power of the electric network

33. Tariffs for services for the transmission of electrical energy are established taking into account the use by consumers of these services of the power of the electrical network to which they are directly technologically connected.

34. The consumer of services must notify the network organization at least 6 months before the next period of tariff regulation about the amount of declared capacity for the coming calendar year, which reflects the degree of use of power of the electrical network by the consumer of services.

The amount of declared power is determined for each point of connection and cannot exceed the maximum connected power at the corresponding point of connection to the network of this service consumer.

In the absence of the specified notification about the value of the declared power, when setting tariffs, the value of the maximum connected power of the power receiving device (power installation) of the service consumer is accepted.

When determining the basis for setting tariffs for the next regulation period, the grid organization has the right to use in relation to consumers of services that systematically exceed the amount of declared power, the amount of power declared by the consumer for the next regulation period or the actual amount of power used for the past period.

35. Tariffs for services for the transmission of electrical energy are established in accordance with the principles of pricing for electrical and thermal energy in the Russian Federation and the rules of state regulation and application of tariffs for electrical and thermal energy in the Russian Federation, taking into account paragraph 34 of these Rules.

Taking into account the degree of power utilization of the electric network when determining the tariff for electric energy transmission services is carried out in accordance with the methodological instructions approved by the federal executive body on tariffs.

V. The procedure for determining losses in electrical networks and paying for these losses

36. Actual losses of electrical energy in electrical networks are defined as the difference between the volume of electrical energy supplied to the electrical network from other networks or from electricity producers, and the volume of electrical energy consumed by power receiving devices connected to this network, as well as transmitted to other networks organizations.

37. Grid organizations are obliged to compensate for actual losses of electrical energy that occurred in their network facilities, minus the losses included in the price of electrical energy.

38. Consumers of services, with the exception of producers of electrical energy, are required to pay, as part of the fee for services for the transmission of electrical energy, regulatory losses arising during the transmission of electrical energy through the network of a network organization with which the relevant persons have concluded an agreement, with the exception of losses included in the price (tariff) for electrical energy, in order to avoid double metering. Consumers of services pay for losses of electrical energy in excess of the standard if it is proven that the losses arose through the fault of these consumers of services.

39. The amount of electrical energy losses in electrical networks, which is included in the fee for services for the transmission of electrical energy, is determined based on the standard for electrical energy losses. Loss standards are established by the authorized federal executive body in accordance with these Rules and the methodology for determining standard and actual losses of electrical energy in electrical networks.

40. Standards for losses of electrical energy in electrical networks are established in relation to the totality of power transmission lines and other electrical grid facilities belonging to the relevant network organization, taking into account differentiation by network voltage levels when setting tariffs for services for the transmission of electrical energy.

41. The methodology for determining standard and actual losses of electrical energy in electrical networks should provide for the calculation of losses based on:

technical characteristics of power lines and other power grid facilities that determine the amount of variable losses in accordance with the technology of transmission and conversion of electrical energy;

standard conditionally constant losses for power lines, power transformers and other power grid facilities;

standard losses in electrical energy measuring instruments.

When establishing standards, the technical condition of power lines and other power grid facilities may also be taken into account.

42. Network organizations purchase electrical energy in order to compensate for electrical energy losses in their networks:

on the wholesale electricity market;

if the grid organization is not a participant in the wholesale electricity market, - on the retail electricity market at the place of its activity.

VI. The procedure for provision and disclosure by network organizations of information on the capacity of electrical networks, their technical characteristics and the cost of services for the transmission of electrical energy

43. Information about the capacity of electrical networks and their technical characteristics is disclosed by the network organization in accordance with the standards for the disclosure of information by subjects of the wholesale and retail electricity markets.

44. The network organization discloses information on the technical characteristics of electrical networks quarterly no later than 30 working days from the end of the quarter.

45. The network organization is obliged to provide information on the availability of capacity of electrical networks and on the cost of services for the transmission of electrical energy upon request (in writing) of the service consumer.

46. ​​The requested information must be provided within 7 days from the date of receipt of the request with reimbursement by the service consumer of the costs of its provision actually incurred by the network organization.

47. Documents containing the requested information must be prepared in accordance with the established procedure by network organizations.

48. The grid organization is responsible for the timeliness, completeness and accuracy of the information provided and disclosed in the manner established by the legislation of the Russian Federation.

VII. The procedure for considering applications (complaints) regarding the provision of access to services for the transmission of electrical energy and making decisions on these applications (complaints) that are binding on legal entities and individuals

49. The basis for initiating and considering cases on issues of providing access to services for the transmission of electrical energy, making decisions and issuing orders by the antimonopoly authority are statements of government authorities or statements (complaints) of legal entities and individuals.

50. The application (complaint) must contain information about the applicant and the person against whom the application (complaint) was filed, a description of the violation of the requirements of these Rules, as well as the demands that the applicant is making.

51. The antimonopoly authority considers the application (complaint) within a month from the date of its receipt.

In case of insufficiency or absence of evidence allowing one to come to a conclusion about the presence or absence of signs of violation of the requirements of these Rules, the antimonopoly authority has the right to collect and analyze additional evidence to extend the period for consideration of the application (complaint) to 3 months from the date of its receipt. The antimonopoly authority is obliged to notify the applicant in writing about the extension of the period for consideration of the application (complaint).

52. If there are no signs of violation of the requirements of these Rules and antimonopoly legislation, the antimonopoly authority notifies the applicant in writing within 10 days from the date of the decision.

53. Cases of violations of antimonopoly legislation are considered by the antimonopoly authority in accordance with the legislation of the Russian Federation.

54. The consideration of cases of violations of the requirements of these Rules in terms of providing access to services for the transmission of electrical energy and antimonopoly legislation and the adoption of decisions (instructions) on them are carried out in the manner established by the federal antimonopoly body.

55. Federal executive authorities, executive authorities of constituent entities of the Russian Federation, local governments, other bodies or organizations (their officials) vested with the functions or rights of these authorities, commercial and non-profit organizations (their heads), individuals, including including individual entrepreneurs, have the right to appeal decisions and orders in whole or in part of the antimonopoly authority in the manner established by the legislation of the Russian Federation.

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

RULES FOR NON-DISCRIMINATIVE ACCESS TO OPERATIONAL DISPATCH CONTROL SERVICES IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES

1. These Rules define the general principles and procedure for ensuring non-discriminatory access of subjects of the electric power industry (hereinafter - consumers of services) to services for operational dispatch control in the electric power industry (hereinafter - services) provided by the system operator and other subjects of operational dispatch control (hereinafter - system operator ), as well as the procedure for providing these services.

2. These Rules do not apply to relations related to the provision of services by subordinate subjects of operational dispatch control in the electric power industry to higher-level subjects of operational dispatch control in the electric power industry.

3. Non-discriminatory access to services involves ensuring equal conditions for the provision of services to their consumers, regardless of their organizational and legal form and legal relations with the person providing these services.

4. The system operator is obliged to disclose information regarding access to services and the provision of services in accordance with the standards for disclosure of information by subjects of the wholesale and retail electricity markets.

5. The system operator provides the following services:

a) management of technological operating modes of electric power facilities;

b) medium- and long-term forecasting of the volume of production and consumption of electrical energy;

c) participation in the formation of a reserve of production energy capacities;

d) approval of the removal for repair and decommissioning of electrical grid facilities and energy facilities for the production of electrical and thermal energy, as well as their commissioning after repair;

e) development of daily operating schedules for power plants and electrical networks of the Unified Energy System of Russia;

f) regulation of the frequency of electric current, ensuring the functioning of the system for automatic regulation of the frequency of electric current and power, ensuring the functioning of system and emergency automation;

g) organization and management of parallel operation modes of the Unified Energy System of Russia and electric power systems of foreign countries;

h) participation in the formation and issuance of technological requirements for technological connection of electric power industry entities to the unified national (all-Russian) electric grid and territorial distribution networks, ensuring their operation as part of the Unified Energy System of Russia.

6. Services are provided on the basis of a bilateral agreement on the provision of services for operational dispatch control in the electric power industry (hereinafter referred to as the agreement), as well as on the basis of an agreement on joining the trading system of the wholesale electricity market.

7. The consumer of services can simultaneously be a participant in the contracts specified in paragraph 6 of these Rules only under the following conditions:

the provisions of these agreements regarding the provision of services are completely identical;

the total cost of services provided on the basis of these contracts is determined by the tariffs established by the federal executive body on tariffs.

8. The conclusion of an agreement between the service consumer and the system operator is mandatory for both parties.

9. Wholesale market entities enter into an agreement with the system operator before they enter into an agreement with the organization managing the unified national (all-Russian) electrical network for the provision of services for the transmission of electrical energy through the unified national (all-Russian) electrical network.

10. The price of services is determined by the tariffs established by the federal executive body on tariffs.

11. The consumer of services who intends to conclude an agreement (hereinafter referred to as the applicant) sends to the system operator an application in writing for access to services, which must contain the following information:

details of the service consumer;

points of connection to networks of a network organization;

start dates for services.

The applicant, along with the application, has the right to send the system operator a draft agreement.

12. The system operator, within 30 days from the date of receipt of the application for access to services, is obliged to consider it and make a decision on providing access to services or refusing it.

13. In the absence of the information specified in paragraph 11 of these Rules, the system operator notifies the applicant about this within 3 days and, within 30 days from the date of receipt of the missing information, considers the application for access to services in accordance with paragraph 12 of these Rules.

14. If a decision is made to provide access to services, the system operator is obliged to send the applicant a signed draft agreement.

15. The applicant, who has received a signed draft agreement from the system operator and has no objections to its terms, fills out the agreement in the part related to information about the applicant and sends 1 signed copy of the agreement to the system operator.

16. If the applicant has submitted a draft agreement, and the system operator has no objections to its terms, the latter is obliged to sign it and send 1 signed copy of the agreement to the applicant.

The agreement is considered concluded from the date of its signing by both parties, unless otherwise established by this agreement or a court decision.

17. If a decision is made to refuse to provide access to services, the system operator is obliged to send the applicant a notice in writing and documents justifying the refusal no later than 10 days from the date of receipt of the application specified in paragraph 11 of these Rules.

A refusal to provide access to services may be appealed to the antimonopoly authority and (or) challenged in court.

18. The system operator has the right to refuse to provide access to services in the following cases:

a) the applicant did not provide the information provided for in paragraph 11 of these Rules;

b) the applicant provided false information;

c) the applicant’s energy facilities are located outside the area of ​​his dispatch responsibility.

In this case, the applicant has the right to re-apply to the system operator with an application for access to services. If the grounds for refusal are eliminated, the system operator does not have the right to refuse to provide the applicant with access to services.

19. The provision of services is carried out in order to ensure reliable energy supply and quality of electrical energy that meets the requirements of technical regulations and other mandatory requirements established by regulatory legal acts, and to take measures to ensure the fulfillment of obligations of electricity industry entities under contracts concluded on the wholesale and retail markets of electrical energy.

As part of the provision of services, the system operator is obliged to choose the most cost-effective solution that ensures the safe and trouble-free operation of the technological infrastructure of the electric power industry and the quality of electrical energy that meets the requirements of technical regulations and other mandatory requirements.

20. Consumers of services have the right not to execute operational dispatch commands and orders if their execution poses a threat to human life, the safety of equipment or leads to a violation of the limits and conditions for the safe operation of nuclear power plants.

21. In the event of emergency electrical power conditions, the provision of services is carried out taking into account the specifics established by the legislation of the Russian Federation.

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

RULES OF NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES

1. These Rules define the general principles and procedure for ensuring non-discriminatory access of subjects of the wholesale electricity (capacity) market (hereinafter - subjects of the wholesale market) to services for organizing the functioning of the trading system of the wholesale electricity (capacity) market, organizing wholesale trade in electrical energy and conducting reconciliation and offsetting mutual counter obligations of trading participants (hereinafter referred to as the services) of the administrator of the wholesale market trading system (hereinafter referred to as the administrator), as well as the procedure for providing these services.

2. Non-discriminatory access to administrator services provides for equal conditions for the provision of services to subjects of the wholesale market, regardless of their organizational and legal form and legal relations with the person providing these services.

3. The administrator is obliged to disclose information regarding access to services and their provision in accordance with the standards for disclosure of information by subjects of the wholesale and retail electricity markets.

4. The administrator does not have the right to refuse to provide services to subjects of the wholesale market, except for the cases established by these Rules and the rules of the wholesale electricity market.

5. Administrator services can be provided to the following persons:

included in the list of commercial organizations - subjects of the federal (all-Russian) wholesale electricity (capacity) market, electricity tariffs for which are established by the federal executive body on tariffs, before the rules of the wholesale electricity market come into force;

having received the status of a wholesale market entity in accordance with the rules of the wholesale electricity market by providing the administrator with the documents and information specified in these Rules, and the wholesale market entities signing an agreement on joining the trading system of the wholesale electricity (capacity) market.

6. A legal entity wishing to gain access to the services of an administrator (hereinafter referred to as the applicant) must submit an application for this and submit the following documents to the administrator:

information about the type of wholesale market entity (generating company, energy sales organization, energy supply organization, supplier of last resort, electricity consumer, etc.) to which the applicant corresponds, in accordance with the rules of the wholesale electricity (capacity) market of the transition period;

signed by the authorized person of the applicant, 5 copies of the draft agreement on joining the wholesale electricity (power) market to the trading system in the form approved by the administrator;

the applicant's application form in the prescribed form;

notarized copies of constituent documents;

a notarized copy of the certificate of state registration of a legal entity;

a notarized copy of the certificate of registration of the applicant with the tax authorities of the Russian Federation;

documents confirming the powers of persons representing the interests of the applicant;

a document confirming the assignment of the organization to the status of a guaranteeing supplier in cases and in the manner established by the legislation of the Russian Federation;

a single-line diagram of connection to an external electrical network, agreed upon with the owner or other legal owner of the network facilities to which the applicant or third parties whose interests he represents are technologically connected, indicating the names and voltage levels of the buses of external substations, proposed groups of delivery points, and places of connection of devices commercial metering, voltage measuring transformers and balance sheet boundaries certified by representatives of adjacent owners of electrical networks;

acts of delimitation of balance sheet ownership and operational responsibility, agreed upon with the owners or other legal owners of network facilities to which the applicant or third parties whose interests the applicant intends to represent are technologically connected.

An applicant who has the right to purchase and sell electrical energy (power) in the regulated sector is required to submit to the administrator a document confirming the inclusion of the legal entity in the list of commercial organizations - subjects of the federal (all-Russian) wholesale electrical energy (capacity) market, the tariffs for electrical energy for which are established by the federal executive body on tariffs.

In order to confirm the compliance of generating and energy-receiving equipment with the quantitative characteristics presented for facilities participating in the wholesale electricity market, the applicant submits to the administrator the passport technological characteristics of the specified equipment.

7. An applicant representing the interests of third parties in the wholesale electricity (capacity) market provides the administrator with information on the technological characteristics of the generating equipment of the suppliers whose interests he represents, and (or) the technological characteristics of the energy receiving equipment of the consumers whose interests he represents.

An applicant carrying out activities in the transmission of electrical energy and purchasing electrical energy on the wholesale electrical energy (power) market, in order to compensate for losses in electrical networks, submits to the administrator the characteristics of the electrical network and network facilities for each group of supply points (network facility).

In order to obtain data on the actual production and consumption of energy, as well as to carry out settlements on the wholesale electricity (capacity) market, the applicant submits documents indicating that the commercial accounting system complies with the mandatory technical requirements and the terms of the agreement on joining the trading system of the wholesale electricity (capacity) market ), in a manner determined by the administrator.

All documents must be submitted by the applicant in accordance with the requirements determined by the administrator.

The administrator has no right to demand the provision of information not provided for by these Rules, unless otherwise established by the legislation of the Russian Federation.

In order to ensure equal access to the administrator’s services, the owner or other legal owner of network facilities to which the applicant or third parties whose interests he represents is technologically connected is obliged to ensure approval of a single-line connection diagram to the external electrical network and draw up acts of delimitation of balance sheet responsibility.

8. The administrator has the right to refuse access to the administrator’s services if the applicant:

a) did not submit the documents and information provided for in paragraph 6 of these Rules;

b) provided false information;

c) does not comply with any of the requirements established by the legislation of the Russian Federation for subjects of the wholesale market.

The applicant has the right to re-apply to the administrator for access to the administrator’s services if the grounds for denying the applicant access to the administrator’s services are eliminated.

9. The decision to deny access to the administrator’s services may be appealed in the manner established by the legislation of the Russian Federation.

10. The administrator provides services to subjects of the wholesale market on the basis of an agreement on joining the trading system of the wholesale electricity market.

A signed copy of the agreement on joining the trading system of the wholesale electricity (power) market is sent by the administrator to the wholesale market entity.

11. Administrator services are paid by the wholesale market entity at tariffs approved by the federal executive body for tariffs.

12. In the event of non-payment of administrator services by a wholesale market entity, the administrator has the right to suspend the acceptance of applications from a wholesale market entity to participate in the procedure for competitive selection of price applications in the free trade sector of the wholesale market until the debt is fully repaid.

13. The administrator has the right to stop providing services to a wholesale market entity in the event of:

non-compliance of a legal entity with the requirements for a wholesale market entity;

loss of the status of a wholesale market entity by a legal entity;

repeated failure or improper fulfillment by a wholesale market entity of obligations to pay for administrator services;

termination of the agreement on joining the wholesale market trading system;

termination of the activities of a wholesale market entity on the grounds provided for by the legislation of the Russian Federation.

1. These Rules determine the procedure for technological connection of energy receiving devices (power installations) of legal entities and individuals (hereinafter referred to as energy receiving devices), regulate the procedure for technological connection, determine the essential terms of the agreement on the implementation of technological connection to electrical networks (hereinafter referred to as the agreement), establish requirements for issuance of individual technical conditions for connection to electrical networks (hereinafter referred to as technical conditions) and criteria for the presence (absence) of the technical possibility of technological connection.

2. These Rules apply to persons whose power receiving devices were previously connected to the electrical network and who declared the need to review (increase) the amount of connected power.

3. The grid organization is obliged to carry out, in relation to any person who contacts it, measures for the technological connection of newly commissioned, newly built, expanding their previously connected capacity and reconstructed power receiving devices to their electrical networks (hereinafter referred to as technological connection), subject to their compliance with these Rules and the availability of technical capabilities for technological connection.

In relation to power receiving devices technologically connected to the electrical network before the entry into force of these Rules, the contract is not concluded and the measures specified in paragraph 12 of these Rules are not carried out.

4. Any persons have the right to technological connection of power transmission lines they have built to electrical networks in accordance with these Rules.

5. When connecting power plants to the distribution devices of a power plant, the latter performs the functions of a network organization in terms of carrying out activities under the contract.

6. Technological connection is carried out on the basis of an agreement concluded with the grid organization within the time limits established by these Rules. The conclusion of an agreement is mandatory for a network organization. In the event of an unjustified refusal or evasion by a network organization from concluding a contract, the interested party has the right to file a claim in court to compel the conclusion of the contract and to recover damages caused by such an unjustified refusal or evasion.

7. These Rules establish the following procedure for technological connection:

filing an application for technological connection with a requirement to issue technical specifications;

preparation of technical specifications and submission of a draft agreement including technical specifications;

conclusion of an agreement;

compliance with technical conditions on the part of the connected person and on the part of the network organization;

performing actions to connect and ensure operation of the power receiving device in the electrical network;

checking compliance with technical conditions and drawing up an act on technological connection.

II. The procedure for concluding and fulfilling the contract

8. To obtain technical conditions and carry out technological connection, the person who owns the power receiving device sends an application for technological connection (hereinafter referred to as the application) to the network organization to whose electrical network the technological connection is planned.

9. The application must include the following information:

a) full name of the applicant;

b) location of the applicant;

c) the postal address of the applicant;

d) a plan for the location of the power receiving device in relation to which it is planned to carry out measures for technological connection;

e) maximum power of the energy receiving device and its technical characteristics, number, power of generators and transformers connected to the network;

f) the number of points of connection to the electrical network, indicating the technical parameters of the elements of electrical installations connected at specific points of the electrical network;

g) a single-line diagram of the applicant’s electrical networks connected to the networks of the grid organization, indicating the possibility of redundancy from its own energy supply sources (including redundancy of its own needs) and the possibility of switching loads (generation) through the applicant’s internal networks;

h) the declared level of reliability of the power receiving device;

i) the nature of the load of the electrical energy consumer (for generators - the possible speed of increasing or decreasing the load) and the presence of loads that distort the shape of the electric current curve and cause voltage asymmetry at connection points;

j) the value and justification of the value of the technological minimum (for generators) and emergency armor (for consumers of electrical energy);

k) permission from the authorized state supervision body to allow the power receiving device into operation (except for facilities under construction);

l) the scope of possible participation in automatic or operational emergency power control (for power plants and consumers, with the exception of individuals) in the provision of services in accordance with a separate agreement;

m) the scope of possible participation in normalized primary frequency regulation and secondary power regulation (for power plants) in the provision of services in accordance with a separate agreement;

o) list and capacity of consumer's current collectors (except for individuals), which can be turned off using an emergency automatic device.

The list of information provided in the application is exhaustive.

The grid organization has no right to demand the provision of information not provided for by these Rules.

10. The grid organization is obliged to send a draft agreement to the applicant for approval within 30 days from the date of receipt of the application.

If the information specified in paragraph 9 of these Rules is missing, or is provided incompletely, the network organization notifies the applicant within 6 working days and considers the application within 30 days from the date of receipt of the missing information.

If the technological connection of power receiving devices is particularly complex for the organization managing the unified national (all-Russian) electrical network or other owners of such network facilities, the specified period by agreement of the parties can be increased to 90 days. The applicant is notified of the increase in the period and the reasons for its change.

11. The agreement must contain the following essential conditions: measures for technological connection and the obligations of the parties to implement them;

fulfillment of technical conditions;

deadlines for the grid organization to carry out technological connection activities;

the amount of fees for carrying out technological connection activities;

responsibility of the parties for fulfilling the terms of the agreement;

boundaries of delineation of balance sheet ownership.

12. Activities for technological connection include:

a) development of a power supply scheme;

b) technical inspection (inspection) of connected power receiving devices by an authorized government body with the participation of representatives of the network organization;

c) preparation and issuance of technical specifications;

d) compliance with technical conditions (on the part of the person whose power receiving device is connected, and on the part of the network organization);

e) actual actions to connect and ensure operation of the power receiving device in the electrical network;

f) checking compliance with technical conditions and drawing up an act on technological connection.

The list of activities for technological connection is exhaustive.

It is prohibited to impose services not provided for by these Rules on a person interested in technological connection.

13. The network organization is obliged, within 30 days from the date of receipt of the application, to consider it, prepare technical conditions for technological connection and agree on them with the system operator (subject of operational dispatch control), and the organization for managing the unified national (all-Russian) electrical network or other owners objects of such a network in the cases provided for in paragraph three of clause 10 of these Rules - within 90 days.

The grid organization is obliged, within 5 days from the date of receipt of the application, to send a copy of it for consideration by the system operator (subject of operational dispatch control), and then, together with him, review it and prepare technical conditions for technological connection.

14. Technical conditions for technological connection are an integral part of the contract.

The technical specifications must indicate:

a) circuits for issuing or receiving power and points of connection to the electrical network (power lines or base substations);

b) justified requirements for strengthening the existing electrical network in connection with the connection of new capacities (construction of new power lines, substations, increasing the cross-section of wires and cables, increasing the capacity of transformers, expanding distribution devices, installing compensating devices to ensure the quality of electricity);

c) calculated values ​​of short circuit currents, requirements for relay protection, voltage regulation, emergency automation, telemechanics, communications, insulation and overvoltage protection, as well as for electrical energy and power metering devices in accordance with the requirements established by regulatory legal acts;

d) requirements for equipping power plants with emergency automatic equipment for issuing power and for equipping consumers with emergency automatic devices;

e) requirements for equipping with devices that ensure the participation of power plants or consumers in automatic or operational emergency power control in the provision of services in accordance with a separate contract;

f) requirements for equipping with devices that ensure the participation of power plants in normalized primary frequency regulation and in secondary power regulation in the provision of services in accordance with a separate contract.

III. Criteria for the presence (absence) of technical possibility of technological connection

15. The criteria for the availability of technical possibility of technological connection are:

a) the location of the power receiving device, in respect of which an application for technological connection has been submitted, within the territorial boundaries of service of the corresponding network organization;

b) no restrictions on connected power in the network node to which the technological connection is to be made.

If any of the specified criteria is not met, there is no technical possibility of technological connection.

In order to verify the validity of the network organization’s determination of the lack of technical feasibility, the applicant has the right to apply to the authorized federal executive body for technological supervision to obtain an opinion on the presence (absence) of the technical possibility of technological connection by the network organization.

16. Restrictions on the connection of additional power arise if the full use of the consumed (generating) power of all previously connected consumers of services for the transmission of electrical energy and the power of the newly connected power receiving device can lead to the load of the energy equipment of the network organization exceeding the values ​​​​defined by technical standards and standards approved or adopted in the manner established by the legislation of the Russian Federation.

17. If there is a restriction on connecting new power, it is allowed to connect power receiving devices to electrical networks within the power value that does not cause restrictions on the use of consumed (generating) power of all electrical energy consumers previously connected to a given network node, or in the declared volume in agreement with the specified consumers.

The Zakonbase website contains the RF Government Decree dated December 27, 2004 N 861 “ON APPROVAL OF THE RULES FOR NON-DISCRIMINATIVE ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATIVE ACCESS TO OPERA SERVICES TECHNIC DISPATCH MANAGEMENT IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES, RULES NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEIVING DEVICES (ENERGY INSTALLATIONS) OF LEGAL AND INDIVIDUALS TO ELECTRIC NETWORKS" in the most latest edition. It is easy to comply with all legal requirements if you read the relevant sections, chapters and articles of this document for 2014. To find the necessary legislative acts on a topic of interest, you should use convenient navigation or advanced search.

On the Zakonbase website you will find the RF Government DECREE dated December 27, 2004 N 861 "ON APPROVAL OF THE RULES FOR NON-DISCRIMINATIVE ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATIVE ACCESS TO OPERATION SERVICES ACTIVE DISPATCH MANAGEMENT IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES, RULES OF NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEIVING DEVICES (ENERGY INSTALLATIONS) LEGAL AND PHYSICAL FACES TO ELECTRIC NETWORKS" in a fresh and complete version, in which all changes and amendments have been made. This guarantees the relevance and reliability of the information.

At the same time, download the RESOLUTION of the Government of the Russian Federation of December 27, 2004 N 861 “ON APPROVAL OF THE RULES FOR NON-DISCRIMINATIONAL ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATIVE ACCESS TO OPERATIONAL DISP SERVICES ETCHER MANAGEMENT IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES, RULES OF NON-DISCRIMINATION ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES AND THE RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEIVING DEVICES (POWER INSTALLATIONS) OF LEGAL AND INDIVIDUALS TO ELECTRIC NETWORKS" free, both in full and in individual chapters.

Russian Federation

Decree of the Government of the Russian Federation of December 27, 2004 N 861 "ON APPROVAL OF THE RULES FOR NON-DISCRIMINATORY ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATORY ACCESS TO OPERATIONAL DISPATCHER SERVICES WHO IS MANAGED IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE TRADE ADMINISTRATOR WHOLESALE MARKET SYSTEMS AND PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEPTION DEVICES (POWER INSTALLATIONS) OF LEGAL AND INDIVIDUALS TO ELECTRIC NETWORKS"


In order to promote the development of competition in the market for the production and sale of electrical energy, to protect the rights of consumers of electrical energy and in accordance with articles , , and the Federal Law "On Electric Power Industry", the Government of the Russian Federation decides:

1. Approve the attached:

Rules for non-discriminatory access to electric energy transmission services and the provision of these services;

Rules for non-discriminatory access to services for operational dispatch control in the electric power industry and the provision of these services;

Rules for non-discriminatory access to the services of the administrator of the wholesale market trading system and the provision of these services;

Rules for the technological connection of energy receiving devices (power installations) of legal entities and individuals to electrical networks.

2. Designate the Federal Antimonopoly Service as the authorized federal executive body to ensure state control over compliance with the rules of non-discriminatory access to electric energy transmission services, operational dispatch management services in the electric power industry and trading system administrator services.

3. The Ministry of Industry and Energy of the Russian Federation, within 3 months, develop and approve a methodology for determining standard and actual losses of electrical energy in electrical networks.

Chairman of the Government
Russian Federation
M.FRADKOV

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

1. These Rules define the general principles and procedure for ensuring non-discriminatory access of subjects of the electric power industry (hereinafter - consumers of services) to services for operational dispatch control in the electric power industry (hereinafter - services) provided by the system operator and other subjects of operational dispatch control (hereinafter - system operator ), as well as the procedure for providing these services.

2. These Rules do not apply to relations related to the provision of services by subordinate subjects of operational dispatch control in the electric power industry to higher-level subjects of operational dispatch control in the electric power industry.

3. Non-discriminatory access to services involves ensuring equal conditions for the provision of services to their consumers, regardless of their organizational and legal form and legal relations with the person providing these services.

4. The system operator is obliged to disclose information regarding access to services and the provision of services in accordance with the standards for disclosure of information by subjects of the wholesale and retail electricity markets.

5. The system operator provides the following services:

a) management of technological operating modes of electric power facilities;

b) medium- and long-term forecasting of the volume of production and consumption of electrical energy;

c) participation in the formation of a reserve of production energy capacities;

d) approval of the removal for repair and decommissioning of electrical grid facilities and energy facilities for the production of electrical and thermal energy, as well as their commissioning after repair;

e) development of daily operating schedules for power plants and electrical networks of the Unified Energy System of Russia;

f) regulation of the frequency of electric current, ensuring the functioning of the system for automatic regulation of the frequency of electric current and power, ensuring the functioning of system and emergency automation;

g) organization and management of parallel operation modes of the Unified Energy System of Russia and electric power systems of foreign countries;

h) participation in the formation and issuance of technological requirements for technological connection of electric power industry entities to the unified national (all-Russian) electric grid and territorial distribution networks, ensuring their operation as part of the Unified Energy System of Russia.

6. Services are provided on the basis of a bilateral agreement on the provision of services for operational dispatch control in the electric power industry (hereinafter referred to as the agreement), as well as on the basis of an agreement on joining the trading system of the wholesale electricity market.

7. The consumer of services can simultaneously be a participant in the contracts specified in paragraph 6 of these Rules only under the following conditions:

the provisions of these agreements regarding the provision of services are completely identical;

the total cost of services provided on the basis of these contracts is determined by the tariffs established by the federal executive body on tariffs.

8. The conclusion of an agreement between the service consumer and the system operator is mandatory for both parties.

9. Wholesale market entities enter into an agreement with the system operator before they enter into an agreement with the organization managing the unified national (all-Russian) electrical network for the provision of services for the transmission of electrical energy through the unified national (all-Russian) electrical network.

10. The price of services is determined by the tariffs established by the federal executive body on tariffs.

11. The consumer of services who intends to conclude an agreement (hereinafter referred to as the applicant) sends to the system operator an application in writing for access to services, which must contain the following information:

details of the service consumer;

points of connection to networks of a network organization;

start dates for services.

The applicant, along with the application, has the right to send the system operator a draft agreement.

12. The system operator, within 30 days from the date of receipt of the application for access to services, is obliged to consider it and make a decision on providing access to services or refusing it.

13. In the absence of the information specified in paragraph 11 of these Rules, the system operator notifies the applicant about this within 3 days and, within 30 days from the date of receipt of the missing information, considers the application for access to services in accordance with paragraph 12 of these Rules.

14. If a decision is made to provide access to services, the system operator is obliged to send the applicant a signed draft agreement.

15. The applicant, who has received a signed draft agreement from the system operator and has no objections to its terms, fills out the agreement in the part related to information about the applicant and sends 1 signed copy of the agreement to the system operator.

16. If the applicant has submitted a draft agreement, and the system operator has no objections to its terms, the latter is obliged to sign it and send 1 signed copy of the agreement to the applicant.

The agreement is considered concluded from the date of its signing by both parties, unless otherwise established by this agreement or a court decision.

17. If a decision is made to refuse to provide access to services, the system operator is obliged to send the applicant a notice in writing and documents justifying the refusal no later than 10 days from the date of receipt of the application specified in paragraph 11 of these Rules.

A refusal to provide access to services may be appealed to the antimonopoly authority and (or) challenged in court.

18. The system operator has the right to refuse to provide access to services in the following cases:

a) the applicant did not provide the information provided for in paragraph 11 of these Rules;

b) the applicant provided false information;

c) the applicant’s energy facilities are located outside the area of ​​his dispatch responsibility.

In this case, the applicant has the right to re-apply to the system operator with an application for access to services. If the grounds for refusal are eliminated, the system operator does not have the right to refuse to provide the applicant with access to services.

19. The provision of services is carried out in order to ensure reliable energy supply and quality of electrical energy that meets the requirements of technical regulations and other mandatory requirements established by regulatory legal acts, and to take measures to ensure the fulfillment of obligations of electricity industry entities under contracts concluded on the wholesale and retail markets of electrical energy.

As part of the provision of services, the system operator is obliged to choose the most cost-effective solution that ensures the safe and trouble-free operation of the technological infrastructure of the electric power industry and the quality of electrical energy that meets the requirements of technical regulations and other mandatory requirements.

20. Consumers of services have the right not to execute operational dispatch commands and orders if their execution poses a threat to human life, the safety of equipment or leads to a violation of the limits and conditions for the safe operation of nuclear power plants.

21. In the event of emergency electrical power conditions, the provision of services is carried out taking into account the specifics established by the legislation of the Russian Federation.

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

1. These Rules define the general principles and procedure for ensuring non-discriminatory access of subjects of the wholesale electricity (capacity) market (hereinafter - subjects of the wholesale market) to services for organizing the functioning of the trading system of the wholesale electricity (capacity) market, organizing wholesale trade in electrical energy and conducting reconciliation and offsetting mutual counter obligations of trading participants (hereinafter referred to as the services) of the administrator of the wholesale market trading system (hereinafter referred to as the administrator), as well as the procedure for providing these services.

2. Non-discriminatory access to administrator services provides for equal conditions for the provision of services to subjects of the wholesale market, regardless of their organizational and legal form and legal relations with the person providing these services.

3. The administrator is obliged to disclose information regarding access to services and their provision in accordance with the standards for disclosure of information by subjects of the wholesale and retail electricity markets.

4. The administrator does not have the right to refuse to provide services to subjects of the wholesale market, except for the cases established by these Rules and the rules of the wholesale electricity market.

5. Administrator services can be provided to the following persons:

included in the list of commercial organizations - subjects of the federal (all-Russian) wholesale electricity (capacity) market, electricity tariffs for which are established by the federal executive body on tariffs, before the rules of the wholesale electricity market come into force;

having received the status of a wholesale market entity in accordance with the rules of the wholesale electricity market by providing the administrator with the documents and information specified in these Rules, and the wholesale market entities signing an agreement on joining the trading system of the wholesale electricity (capacity) market.

6. A legal entity wishing to gain access to the services of an administrator (hereinafter referred to as the applicant) must submit an application for this and submit the following documents to the administrator:

information about the type of wholesale market entity (generating company, energy sales organization, energy supply organization, supplier of last resort, electricity consumer, etc.) to which the applicant corresponds, in accordance with the rules of the wholesale electricity (capacity) market of the transition period;

signed by the authorized person of the applicant, 5 copies of the draft agreement on joining the wholesale electricity (power) market to the trading system in the form approved by the administrator;

the applicant's application form in the prescribed form;

notarized copies of constituent documents;

a notarized copy of the certificate of state registration of a legal entity;

a notarized copy of the certificate of registration of the applicant with the tax authorities of the Russian Federation;

documents confirming the powers of persons representing the interests of the applicant;

a document confirming the assignment of the organization to the status of a guaranteeing supplier in cases and in the manner established by the legislation of the Russian Federation;

a single-line diagram of connection to an external electrical network, agreed upon with the owner or other legal owner of the network facilities to which the applicant or third parties whose interests he represents are technologically connected, indicating the names and voltage levels of the buses of external substations, proposed groups of delivery points, and places of connection of devices commercial metering, voltage measuring transformers and balance sheet boundaries certified by representatives of adjacent owners of electrical networks;

acts of delimitation of balance sheet ownership and operational responsibility, agreed upon with the owners or other legal owners of network facilities to which the applicant or third parties whose interests the applicant intends to represent are technologically connected.

An applicant who has the right to purchase and sell electrical energy (power) in the regulated sector is required to submit to the administrator a document confirming the inclusion of the legal entity in the list of commercial organizations - subjects of the federal (all-Russian) wholesale electrical energy (capacity) market, the tariffs for electrical energy for which are established by the federal executive body on tariffs.

In order to confirm the compliance of generating and energy-receiving equipment with the quantitative characteristics presented for facilities participating in the wholesale electricity market, the applicant submits to the administrator the passport technological characteristics of the specified equipment.

7. An applicant representing the interests of third parties in the wholesale electricity (capacity) market provides the administrator with information on the technological characteristics of the generating equipment of the suppliers whose interests he represents, and (or) the technological characteristics of the energy receiving equipment of the consumers whose interests he represents.

An applicant carrying out activities in the transmission of electrical energy and purchasing electrical energy on the wholesale electrical energy (power) market, in order to compensate for losses in electrical networks, submits to the administrator the characteristics of the electrical network and network facilities for each group of supply points (network facility).

In order to obtain data on the actual production and consumption of energy, as well as to carry out settlements on the wholesale electricity (capacity) market, the applicant submits documents indicating that the commercial accounting system complies with the mandatory technical requirements and the terms of the agreement on joining the trading system of the wholesale electricity (capacity) market ), in a manner determined by the administrator.

All documents must be submitted by the applicant in accordance with the requirements determined by the administrator.

The administrator has no right to demand the provision of information not provided for by these Rules, unless otherwise established by the legislation of the Russian Federation.

In order to ensure equal access to the administrator’s services, the owner or other legal owner of network facilities to which the applicant or third parties whose interests he represents is technologically connected is obliged to ensure approval of a single-line connection diagram to the external electrical network and draw up acts of delimitation of balance sheet responsibility.

8. The administrator has the right to refuse access to the administrator’s services if the applicant:

a) did not submit the documents and information provided for in paragraph 6 of these Rules;

b) provided false information;

c) does not comply with any of the requirements established by the legislation of the Russian Federation for subjects of the wholesale market.

The applicant has the right to re-apply to the administrator for access to the administrator’s services if the grounds for denying the applicant access to the administrator’s services are eliminated.

9. The decision to deny access to the administrator’s services may be appealed in the manner established by the legislation of the Russian Federation.

10. The administrator provides services to subjects of the wholesale market on the basis of an agreement on joining the trading system of the wholesale electricity market.

A signed copy of the agreement on joining the trading system of the wholesale electricity (power) market is sent by the administrator to the wholesale market entity.

11. Administrator services are paid by the wholesale market entity at tariffs approved by the federal executive body for tariffs.

12. In the event of non-payment of administrator services by a wholesale market entity, the administrator has the right to suspend the acceptance of applications from a wholesale market entity to participate in the procedure for competitive selection of price applications in the free trade sector of the wholesale market until the debt is fully repaid.

13. The administrator has the right to stop providing services to a wholesale market entity in the event of:

non-compliance of a legal entity with the requirements for a wholesale market entity;

loss of the status of a wholesale market entity by a legal entity;

repeated failure or improper fulfillment by a wholesale market entity of obligations to pay for administrator services;

termination of the agreement on joining the wholesale market trading system;

termination of the activities of a wholesale market entity on the grounds provided for by the legislation of the Russian Federation.

14. The adoption by the administrator, in accordance with the rules of the wholesale electricity (power) market of the transition period and the agreement on joining the trading system of the wholesale electricity market, of a decision to recognize the sale (purchase) of electricity in the free trade sector in general or in any limited territory failed cannot be considered as non-fulfillment or improper fulfillment of obligations to provide administrator services.

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

---

It does not work Editorial from 31.08.2006

Name of documentDecree of the Government of the Russian Federation of December 27, 2004 N 861 (as amended on August 31, 2006) “ON APPROVAL OF THE RULES FOR NON-DISCRIMINATIVE ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATION ACCESS TO ELECTRIC ENERGY LUGA ON OPERATIONAL DISPATCH CONTROL IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES , RULES OF NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEIVING DEVICES (ENERGY INSTALLATIONS) OF LEGAL AND PHYSICAL THEIR FACES TO ELECTRIC NETWORKS"
Document typedecree, rules
Receiving authorityRussian government
Document Number861
Acceptance date01.01.1970
Revision date31.08.2006
Date of registration with the Ministry of Justice01.01.1970
StatusIt does not work
Publication
  • The document was not published in this form
  • Document in electronic form FAPSI, STC "System"
  • (as amended on December 27, 2004 - "Rossiyskaya Gazeta", No. 7, January 19, 2005;
  • "Collection of Legislation of the Russian Federation", N 52, 12/27/2004, part 2, art. 5525)
NavigatorNotes

Decree of the Government of the Russian Federation of December 27, 2004 N 861 (as amended on August 31, 2006) “ON APPROVAL OF THE RULES FOR NON-DISCRIMINATIVE ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES FOR NON-DISCRIMINATION ACCESS TO ELECTRIC ENERGY LUGA ON OPERATIONAL DISPATCH CONTROL IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES , RULES OF NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEIVING DEVICES (ENERGY INSTALLATIONS) OF LEGAL AND PHYSICAL THEIR FACES TO ELECTRIC NETWORKS"

In order to promote the development of competition in the market for the production and sale of electrical energy, to protect the rights of consumers of electrical energy and in accordance with articles , , and the Federal Law "On Electric Power Industry", the Government of the Russian Federation decides:

1. Approve the attached:

Rules for non-discriminatory access to electric energy transmission services and the provision of these services;

Rules for non-discriminatory access to services for operational dispatch control in the electric power industry and the provision of these services;

Rules for non-discriminatory access to the services of the administrator of the wholesale market trading system and the provision of these services;

Rules for the technological connection of energy receiving devices (power installations) of legal entities and individuals to electrical networks.

2. Designate the Federal Antimonopoly Service as the authorized federal executive body to ensure state control over compliance with the rules of non-discriminatory access to electric energy transmission services, operational dispatch management services in the electric power industry and trading system administrator services.

3. The Ministry of Industry and Energy of the Russian Federation, within 3 months, develop and approve a methodology for determining standard and actual losses of electrical energy in electrical networks.

Chairman of the Government
Russian Federation
M.FRADKOV

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

RULES OF NON-DISCRIMINATIONAL ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND PROVISION OF THESE SERVICES

dated August 31, 2006 N 530)

I. General provisions

1. These Rules define the general principles and procedure for ensuring non-discriminatory access to electric energy transmission services, as well as the provision of these services.

2. The terms used in these Rules mean the following:

“territorial distribution network” - a complex of power lines and equipment not included in the unified national (all-Russian) electrical network used to provide services for the transmission of electrical energy;

Grid organizations" - organizations that own, by right of ownership or on another basis established by federal laws, electric grid facilities, with the use of which such organizations provide services for the transmission of electrical energy, and also carry out, in the prescribed manner, the technological connection of power receiving devices (power installations) of legal and physical entities. persons to electrical networks;

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

“point of connection to the electrical network” - the place of physical connection of the power receiving device (power installation) (hereinafter referred to as the power receiving device) of the consumer of electric energy transmission services (hereinafter referred to as the consumer of services) with the electrical network of the network organization;

“electric network throughput” is the technologically maximum permissible value of power that can be transmitted taking into account operating conditions and reliability parameters of the functioning of electric power systems;

“balance sheet boundary” is the line of dividing electric grid facilities between owners on the basis of ownership or possession on another legal basis.

Other concepts used in these Rules correspond to the concepts defined by the legislation of the Russian Federation.

3. Non-discriminatory access to electric energy transmission services involves ensuring equal conditions for the provision of these services to their consumers, regardless of the organizational and legal form and legal relations with the person providing these services.

4. Grid organizations are required to disclose information regarding access to electric energy transmission services and the provision of these services in accordance with the standards for information disclosure by subjects of the wholesale and retail electric energy markets.

Clause 5 - Lost force.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

6. Services for the transmission of electrical energy are provided by the network organization on the basis of an agreement on the paid provision of services for the transmission of electrical energy to persons who, by right of ownership or on another legal basis, have power receiving devices and other electric power facilities technologically connected in the prescribed manner to the electrical network, as well as subjects of the wholesale electricity market exporting (importing) electricity, energy sales organizations and guaranteeing suppliers.

Persons who own, by right of ownership or on another legal basis, electric grid facilities to which power receiving devices of service consumers are connected, provide services for the transmission of electrical energy to these consumers on a paid contractual basis. These persons participate in relations for the provision of services for the transmission of electrical energy to consumers of services in accordance with the provisions of these Rules provided for network organizations.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

The activity of a consumer (producer) of electrical energy who uses electrical energy when renting out residential and non-residential premises belonging to him, leasing them and (or) operating them, or transferring them to third parties on other legal grounds is not recognized as the provision of services for the transmission of electrical energy.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

If the power receiving devices of the service consumer are connected to the electrical networks of the network organization through the power installations of electrical energy producers or are connected to ownerless facilities of the electrical grid, the agreement for the provision of services for the transmission of electrical energy (hereinafter referred to as the agreement) is concluded with the network organization to whose networks they are connected. power plants of the specified manufacturers or ownerless power grid facilities.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

Consumers of services connected to the electrical networks of the network organization through energy installations power stations, pay for services for the transmission of electrical energy at tariffs established in accordance with methodological guidelines approved by the federal executive body on tariffs.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

7. In order to ensure the fulfillment of its obligations under contracts to consumers of services - buyers and sellers of electrical energy - the grid organization enters into contracts with other grid organizations whose power grid facilities have a technological connection to power grid facilities owned or on another legal basis by of this network organization (hereinafter referred to as adjacent network organizations), in accordance with section II.1 of these Rules.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

8. During the transition period of operation of the electric power industry, the provision of services for the transmission of electrical energy using facilities included in the unified national (all-Russian) electrical network is carried out on the basis of an agreement concluded both on behalf of the organization for managing the unified national (all-Russian) electrical network, and from on behalf of other owners of these objects.

II. The procedure for concluding and executing an agreement

9. The agreement is public and mandatory for the network organization.

Unreasonable evasion or refusal by a network organization to conclude an agreement may be appealed by the consumer of services in the manner established by the legislation of the Russian Federation.

10. An agreement cannot be concluded before the conclusion of an agreement on the technological connection of energy receiving devices (power installations) of legal entities and individuals to electrical networks, except for cases where the consumer of services is:

a person whose power receiving device was technologically connected to the electrical network before these Rules came into force;

a person who exports (imports) electrical energy and does not own, use or dispose of electrical power facilities connected to the electrical network;

an energy sales organization (supplier of last resort) that enters into an agreement in the interests of the consumers of electrical energy it serves.

In relation to these persons, the network organization has the right, in order to determine the technical characteristics of power receiving devices (power installations) necessary for the provision of services for the transmission of electrical energy, to request information and documentation necessary for technological connection.

11. Under the contract, the network organization undertakes to carry out a set of organizationally and technologically related actions that ensure the transmission of electrical energy through technical devices of electrical networks, and the consumer of services - to pay for them.

12. The contract must contain the following essential terms:

the maximum power value of the power receiving device connected to the electrical network, with the distribution of the specified value for each connection point of the electrical network in respect of which technological connection was carried out in the manner established by the legislation of the Russian Federation;

the amount of power (generating or consumed) within which the network organization undertakes to ensure the transmission of electrical energy at the connection points specified in the contract;

responsibility of the service consumer and the network organization for the condition and maintenance of electric grid facilities, which is determined by their balance sheet and is recorded in the act of delimitation of the balance sheet of electric grids and the operational responsibilities of the parties attached to the contract;

the amount of technological and emergency reservation (for consumers - legal entities or entrepreneurs without forming a legal entity who meet the relevant requirements established by the legislation of the Russian Federation in the field of electric power industry), which must be taken into account when determining the procedure for limiting the power consumption regime. For these persons, the act of approval of emergency and technological armor is a mandatory annex to the contract;

obligations of the parties to equip connection points with means of measuring electrical energy, including measuring instruments that comply with the requirements established by the legislation of the Russian Federation, as well as ensuring their operability and compliance during the entire term of the contract with operational requirements for them established by the authorized body for technical regulation and metrology and the manufacturer, or a calculated method of metering electrical energy used in the absence of metering devices.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

13. The service consumer assumes the following obligations in accordance with the contract:

pay the network organization for services for the transmission of electrical energy within the terms and amounts established by the contract;

maintain the relay protection and emergency automation equipment, electricity and power metering devices, as well as other devices necessary to maintain the required parameters of reliability and quality of electricity, which are in his possession or on another legal basis, and comply with the requirements during the entire term of the contract , established for technological connection and in the operating rules of the specified means, instruments and devices;

submit to the network organization, within the time limits established by the contract, the necessary technological information: main electrical diagrams, equipment characteristics, diagrams of relay protection devices and emergency automation, operational data on the technological operating modes of the equipment;

inform the network organization within the time limits established by the contract about emergencies at energy facilities, planned, current and major repairs at them;

inform the network organization about the scope of participation in automatic or operational emergency power control, in normalized primary frequency regulation and in secondary power regulation (for power plants), as well as about the list and power of the service consumer's current collectors that can be turned off by emergency automatic devices;

fulfill obligations to ensure the safe operation of energy networks under their control and the serviceability of the instruments and equipment they use related to the transmission of electrical energy;

freely admit authorized representatives of the grid organization to the points of control and recording of the quantity and quality of transferred electrical energy in the manner established by the agreement.

14. The grid organization assumes the following obligations in accordance with the agreement:

ensure the transfer of electrical energy to the energy receiving devices of the service consumer, the quality and parameters of which must comply with technical regulations and other mandatory requirements;

carry out the transfer of electrical energy in accordance with the agreed reliability parameters, taking into account the technological characteristics of power receiving devices (power plants);

in the manner and within the time limits established by the contract, inform the service consumer about emergencies in electrical networks, repair and maintenance work that affect the fulfillment of obligations under the contract;

freely admit authorized representatives of service consumers to points of control and recording of the quantity and quality of transferred electrical energy in the manner established by the contract.

14.1. Consumers of services - buyers of electrical energy must comply with the values ​​​​of the ratio of consumption of active and reactive power, determined in the contract in accordance with the procedure approved by the federal executive body performing the functions of generation public policy in the field of fuel and energy complex. These characteristics are determined by:

a network organization for consumers of services connected to electrical networks with a voltage of 35 kV and below;

The network organization together with the relevant operational dispatch control entity for consumers of services connected to electrical networks with voltages above 35 kV.

If the service consumer deviates from the contractually established values ​​of the ratio of consumption of active and reactive power as a result of participation in the regulation of reactive power under an agreement with the grid organization, he pays for services for the transmission of electrical energy, including as part of the final tariff (price) for electrical energy supplied to him under an energy supply contract, taking into account a reduction factor established in accordance with methodological guidelines approved by the federal executive body for tariffs.

If the consumer of services fails to comply with the ratio of active and reactive power consumption established by the contract, except for cases where this was a consequence of the execution of dispatch commands or orders of the subject of operational dispatch control or was carried out by agreement of the parties, he installs and maintains devices that provide regulation of reactive power, or pays for services for the transmission of electrical energy, including as part of the final tariff (price) for electrical energy supplied to it under an energy supply agreement, taking into account the corresponding increasing factor.

Upon detection by the network organization, based on meter readings, of violations of the ratio of active and reactive power consumption, a report is drawn up and sent to the service consumer. The service consumer, within 10 working days from the date of receipt of the act, notifies in writing of the period during which he will ensure compliance established characteristics by self-installation devices providing reactive power regulation, or the impossibility of fulfilling the specified requirement and consent to the application of an increasing factor to the cost of services for the transmission of electrical energy. The specified period cannot exceed 6 months. If, after 10 working days, the notification by the consumer of services has not been sent, the network organization, as well as the guaranteeing supplier (energy supply organization, energy sales organization) under the energy supply agreement, apply an increasing factor to the tariff for electric energy transmission services (including as part of the final tariff (prices) for electrical energy). The increasing factor is applied before the installation of the corresponding devices by the service consumer who has violated the ratio of active and reactive power consumption.

Losses incurred by a network organization or third parties in connection with a violation of the established values ​​of the ratio of active and reactive power consumption are compensated by the person who committed such a violation in accordance with the civil legislation of the Russian Federation.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

14.2. In the case of installation of relay protection devices, emergency and regime automation and (or) its components on the power receiving devices of service consumers, their safety and reliable operation, as well as the possibility of timely execution of control actions in accordance with the requirements of the system operator (subject of operational dispatch control of a technologically isolated territorial electric power system) are provided by the grid organization, unless the contract stipulates that the consumer of the services performs these actions independently.

If, when the consumer of services and the network organization entered into an agreement on technological connection to electric networks, the technical conditions for technological connection did not include requirements for equipping the power receiving devices of the consumer of services with relay protection devices, emergency and operational automation, including devices that provide remote input of temporary shutdown schedules consumption from dispatch centers, the corresponding conditions are provided for in an agreement concluded by the same parties. Measures to equip the power receiving devices of service consumers with relay protection devices, emergency and regime automation in accordance with the requirements of the relevant operational dispatch control entity are carried out by the network organization, unless otherwise established by agreement of the parties, on the basis of a contract.

If the service consumer fails to comply with the terms of the contract relating to the functioning of relay protection devices, emergency and regime automation, the network organization has the right to suspend the fulfillment of its obligations under the contract or refuse to fulfill them.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

15. A person who intends to conclude an agreement (hereinafter referred to as the applicant) sends a written application to the network organization to conclude an agreement, which must contain the following information:

Details of the consumer of electric energy transmission services; volumes and expected mode of transmission of electrical energy broken down by month;

the volume of maximum power and the nature of the load of energy receiving devices (power plants) connected to the network (generating or consumed), with its distribution at each point of connection of the electrical network and indicating the boundaries of the balance sheet;

single-line diagram of the electrical network of a service consumer connected to the networks of a network organization;

points of connection to the networks of the network organization, indicating for each point of connection to the network the declared power values, including the power values ​​during the period of maximum loads of electrical energy consumers;

start date for the provision of electricity transmission services;

reference to the agreement on the provision of services for operational dispatch control (in the case of concluding an agreement on the provision of services for the transmission of electrical energy with an organization for managing the unified national (all-Russian) electrical grid).

16. The network organization, within 30 days from the date of receipt of the application for concluding an agreement, is obliged to consider it and send the applicant a draft agreement signed by the network organization or a reasoned refusal to conclude it.

17. In the absence of information specified in paragraph 15 of these Rules, the network organization notifies the applicant about this within 6 working days and, within 30 days from the date of receipt of the missing information, considers the application in accordance with paragraph 16 of these Rules.

18. The applicant, who has received a draft agreement from the network organization, fills it out in the part related to the information about the applicant included in the agreement, and sends one signed copy of the agreement to the network organization.

19. The agreement is considered concluded from the date it is signed by the applicant, unless otherwise established by the agreement or court decision.

20. The grid organization has the right to refuse to conclude an agreement in the event of:

the consumer of services does not have a concluded agreement on the provision of services for operational dispatch control (in the case of concluding an agreement on the provision of services for the transmission of electrical energy with an organization for managing the unified national (all-Russian) electrical grid);

lack of technical capability to provide services for the transmission of electrical energy in the declared volume (if the volume of power is declared, the proper transmission of which cannot be ensured by the grid organization based on the existing conditions of technological connection);

sending an application to conclude an agreement by a person who does not have a technological connection to the electrical networks of this network organization. At the same time, a mandatory condition for concluding an agreement with guaranteeing suppliers and energy sales organizations is the presence of a technological connection of consumers of electrical energy in whose favor the agreement is concluded, and for organizations engaged in the export-import of electrical energy, the presence of a connection between the electrical networks of this network organization and the electrical networks neighboring states through whose territories export and import supplies of electrical energy are carried out.

If several organizations participating in a competition for the right to operate as a supplier of last resort apply to conclude an agreement, the agreement is concluded with each of the applied organizations. The start date for the provision of services under the contract cannot be earlier than the date from which the relevant organization will be assigned the status of a guaranteeing supplier.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

21. If it is not technically possible to provide services for the transmission of electrical energy within the scope of services declared by the consumer, the network organization is obliged to notify the applicant within 30 days about the conditions and to what extent the service can be provided and the contract can be concluded.

22. If there are grounds for refusal to conclude an agreement, the network organization is obliged, no later than 30 days from the date of receipt of the application specified in paragraph 15 of these Rules, to send to the applicant in writing a reasoned refusal to conclude an agreement with supporting documents attached.

Refusal to conclude an agreement may be challenged in the manner established by the legislation of the Russian Federation.

23. A prerequisite for the provision of services for the transmission of electric energy to the consumer of services is that he has the status of a participant in the wholesale market or has concluded an electric energy purchase and sale agreement with a guarantee supplier, energy sales organization or other supplier of electric energy.

24. The grid organization has the right to suspend the transmission of electrical energy in the following cases:

the occurrence of debt of the consumer of services to pay for electric energy transmission services for 2 or more billing periods;

Violation by the consumer of services of the terms of payment determined by the purchase and sale (supply) agreement of electrical energy, an energy supply agreement or an agreement on joining the trading system of the wholesale electricity (capacity) market - in the presence of appropriate notification (in writing) to the administrator of the trading system, guaranteeing supplier or energy sales organization indicating the amount of debt of the consumer of services, the deadline for its repayment, as well as the expected period for introducing restrictions on the consumption regime;

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

connection by the consumer of services to the electrical network of power receiving devices (power installations) that do not comply with the terms of the contract, or connection carried out in violation of the procedure for technological connection of power receiving devices of legal entities and individuals to electrical networks;

24.1. If a consumer of services (including an energy sales organization) requires the installation of metering devices at power grid facilities owned by the network organization, the consumer of services has the right to send to the network organization an application about the need to equip the delivery point with metering devices, indicating the delivery point to be equipped and the necessary technical requirements to measuring instruments.

The grid organization considers the specified application and, within no more than 15 working days from the date of its receipt, sends to the applicant a document containing technical conditions for carrying out work on equipping the delivery point with measuring instruments (indicating the timing and cost of performing the relevant work), or a justified refusal to due to the technical impossibility of installing the necessary metering devices. Technical specifications cannot include work that is not directly related to the installation of metering devices.

The applicant agrees with the network organization on the timing and cost of the work within no more than 10 working days from the date of receipt of the relevant document.

The period for completing the work cannot exceed 3 months from the date of approval of technical conditions, unless the installation of metering devices requires the creation of new power grid facilities and the introduction of restrictions on the consumption regime in relation to other consumers.

If the applicant agrees with the timing and cost of the work, the network organization carries out work to equip the declared delivery point with metering devices and assumes obligations to ensure proper maintenance of the installed metering devices, unless otherwise established by the relevant agreement.

If the applicant disagrees with the timing and cost of the work, as well as if the network organization violates the deadlines for completing the work, the applicant has the right, in agreement with the network organization, independently or with the involvement of third parties, to carry out work on equipping the delivery point with metering devices.

The operation of metering devices owned by the consumer of services or a third party engaged by him to carry out work on equipping the delivery point with metering devices is carried out at the expense of the owner of these devices.

The applicant has the right to challenge the refusal of the network organization to install metering devices, the technical conditions for their installation, or the requirements imposed by the network organization on persons performing work on its network equipment, in the manner prescribed by the legislation of the Russian Federation.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

Clause 25 - Lost force.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

26. Suspension of the transmission of electrical energy does not entail termination of the contract.

When the transmission of electrical energy is suspended on the grounds provided for in paragraph 24 of these Rules, consumers of services are allowed to partially or completely limit the mode of consumption of electrical energy in the prescribed manner.

The consumer of services cannot be limited in the consumption of electrical energy less than the power value established in the act of approval of emergency and technological armor, except for cases established by the legislation of the Russian Federation.

Clause 27 - Lost force.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

28. An agreement concluded for a certain period is considered extended for the same period and on the same conditions, if before the end of its validity period neither of the parties declares its termination, amendment or conclusion of a new agreement.

If one of the parties before the expiration of the contract makes a proposal to conclude a new contract, then the relations of the parties before concluding a new contract are regulated in accordance with the terms of the previously concluded contract.

If the network organization has grounds for unilateral termination of the contract with the guarantee supplier (energy sales organization) due to its failure to fulfill its obligations to pay for the relevant services, the network organization is obliged to send a notice to consumers of electric energy in whose interests it acts within 10 days from the moment the grounds arise. about the upcoming termination of the contract and a proposal to conclude a contract directly with the network organization.

Termination of the contract does not entail disconnection of the service consumer's power receiving device from the electrical network.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

Clause 29 - Lost force.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

II.1. The procedure for concluding and executing contracts between related network organizations

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

29.1. Under an agreement between related network organizations, one party to the agreement undertakes to provide the other party with services for the transmission of electrical energy using power grid facilities belonging to it by right of ownership or on another legal basis (to provide electrical communications within the limits of the amount of connected (declared) power at the corresponding point of connection and carry out the transmission of electrical energy to the point of connection of the electrical grid facilities of the other party to the electrical networks of this network organization), and the other party undertakes to pay for these services or provide counter-provision of services for the transmission of electrical energy. The service is provided within the limits of the amount of connected (declared) capacity at the corresponding point of technological connection of electric grid facilities of one network organization to the facilities of another network organization. The consumer of the services provided under such an agreement is determined in accordance with clause 29.8 of these Rules.

29.2. When concluding an agreement between adjacent grid organizations, the parties determine the power grid facilities belonging to them by right of ownership or on another legal basis, in relation to which mutual coordination of changes in operational status is necessary, repair work, modernization and other activities (hereinafter referred to as objects of inter-network coordination). The list of objects of inter-network coordination is an integral part of the agreement between adjacent network organizations.

The list of inter-network coordination objects indicates the party making the change (coordinating the change) of the operational state of each object included in the specified list.

The list of objects of inter-grid coordination does not include electric grid facilities that are contained in the lists of dispatch objects of dispatch centers of the system operator or other subjects of operational dispatch control.

The designation of one of the network organizations as the organization making changes (coordinating the implementation of changes) in the operational state of inter-network coordination objects does not affect the price of the contract between adjacent network organizations.

29.3. A network organization does not have the right to refuse to conclude an agreement with an adjacent network organization.

Agreements between related network organizations are concluded in accordance with the civil legislation of the Russian Federation and the legislation of the Russian Federation on the electric power industry, taking into account the specifics established by these Rules.

In the event of an unreasonable refusal or evasion by a network organization from concluding an agreement, the other party has the right to go to court with a demand to compel the conclusion of an agreement and compensation for losses caused to it.

29.4. The validity period of the agreements provided for in this section, concluded with owners of electrical grid facilities included in the unified national (all-Russian) electrical network other than the organization for managing the unified national (all-Russian) electrical network, is limited to the transition period of reform of the electric power industry. Relations related to the further use by such persons of power grid facilities included in the unified national (all-Russian) power grid are regulated on the basis of agreements on the procedure for using power grid facilities included in the unified national (all-Russian) power grid.

At the end of the transition period of reforming the electric power industry, relations for the provision of services for the transmission of electrical energy using power grid facilities included in the unified national (all-Russian) electrical network are settled with the organization for managing the unified national (all-Russian) electrical network, with the exception of those specified in accordance with Article 7 of the Federal Law “On Electric Power Industry” cases when contracts for the provision of services for the transmission of electrical energy using the specified facilities are concluded by the owners of such facilities independently.

Relations related to the provision of services for the transmission of electrical energy using electrical grid facilities owned by the federal state unitary enterprise "Russian State Concern for the Production of Electrical and Thermal Energy at Nuclear Power Plants" are settled on the basis of an agreement with the organization for managing the unified national (all-Russian) electrical network.

29.5. The agreement between related network organizations must contain the following essential terms:

the amount of connected (declared) power, within which the relevant party undertakes to ensure the transmission of electrical energy at the corresponding point of connection;

responsibility of the parties to the agreement for the condition and maintenance of electric grid facilities, which is recorded in the act attached to the agreement delineating the balance sheet ownership of electric grids and the operational responsibilities of the parties;

the procedure for making payments for services rendered, taking into account the features defined in clause 29.8 of these Rules;

Technical characteristics of connection points of electric grid facilities belonging to the parties to the agreement, including their capacity;

A list of objects of inter-network coordination indicating for each object the party making changes (coordinating the implementation of changes) of its operational state, as well as the procedure for ensuring coordination of the parties’ actions when performing such changes and repair work.

29.6. The following conditions can also be regulated by an agreement between related network organizations:

conditions for maintaining the parameters of reliability of power supply and quality of electrical energy that meet the mandatory requirements, including the conditions for parallel operation of electrical networks owned by the parties to the contract, the procedure for equipping power grid facilities belonging to the parties to the contract with relay protection devices, emergency and regime automation (in their absence) and the procedure for interaction between the parties to the contract when setting them up and using them;

the procedure for equipping electrical grid facilities owned by the parties to the contract with electricity and power metering devices and metering the flow of electrical energy through connection points of electrical grid facilities owned by the parties to the contract;

The procedure for mutual notification by the parties to the agreement about actions that may have consequences for the technological operating modes of the power grid facilities of the other party, including the procedure for coordination and mutual notification of repair and maintenance work at the power grid facilities;

the procedure for interaction between the parties to the agreement in the event of the occurrence and elimination of technological disruptions in the operation of power grid facilities owned by the parties;

The scope and procedure for the parties to the contract to provide the necessary technological information: electrical diagrams, equipment characteristics, data on its operating modes and other data necessary to fulfill the terms of the contract.

29.7. When executing the agreement provided for in this section, grid organizations are obliged to:

ensure the operational condition and compliance with the mandatory requirements for operation of relay protection devices, emergency and regime automation, electrical energy and power metering devices belonging to them by right of ownership or on another legal basis, as well as other devices necessary to maintain the required parameters of reliability and quality of electrical energy ;

promptly inform the other party to the contract about the occurrence (threat of occurrence) of emergency situations in the operation of electric grid facilities owned by them, as well as about repair and preventive work carried out at these facilities;

freely admit authorized representatives of the other party to the contract to the points of control and recording of the quantity and quality of transferred electrical energy.

29.8. The consumer of services under an agreement between related network organizations is determined as follows:

when executing an agreement between the owners of electric grid facilities included in the unified national (all-Russian) electric grid and territorial grid organizations, the consumer of services is the territorial grid organization;

when executing an agreement between the organization for managing the unified national (all-Russian) electrical grid and other owners of electrical grid facilities included in the unified national (all-Russian) electrical network, the consumer of services is the other owners of electrical grid facilities included in the unified national (all-Russian) electrical network;

when executing an agreement between territorial grid organizations serving consumers located in the territories of different constituent entities of the Russian Federation, the consumer of services is the one of the two adjacent grid organizations to whose electric networks, following the results of the previous regulatory period, electric energy was transferred in a larger volume than was supplied from its networks, while the cost of services provided is determined in accordance with methodological guidelines approved by the federal executive body on tariffs;

When executing an agreement between territorial grid organizations serving consumers located on the territory of one constituent entity of the Russian Federation, the parties to the agreement mutually provide services for the transmission of electrical energy, with both parties being consumers of the services. When setting tariffs for electric energy transmission services for 2008 and subsequent years, tariff rates are determined taking into account the need to ensure equality of tariffs for electric energy transmission services for all consumers of services located on the territory of the relevant constituent entity of the Russian Federation and belonging to the same group (category) from among those for which the legislation of the Russian Federation provides for differentiation of tariffs for electrical energy (power). By decision of the federal executive body on tariffs, adopted at the request of the authorized executive bodies of the constituent entities of the Russian Federation in the field of state regulation of tariffs, this norm can be applied when setting tariffs for 2007.

Settlements under the agreement concluded by territorial grid organizations in accordance with this section are carried out at the tariff for services for the transmission of electrical energy, which is determined in accordance with the methodological instructions approved by the federal executive body on tariffs in relation to each of the parties to such an agreement and is individual in nature. In this case, the expenses of the territorial network organization for payment for the services provided in accordance with the specified agreement are included in the economically justified expenses taken into account when setting the tariff for services for the transmission of electrical energy for other consumers of its services, and the income of the other party to the specified agreement from the services provided by it under this agreement and income from services for the transmission of electrical energy provided to other consumers must in total provide the necessary gross revenue of this organization.

III. The procedure for accessing electrical networks in conditions of their limited capacity

30. When connecting to the electrical network and concluding an agreement, any consumer of services is assigned the right to receive electrical energy during any period of the agreement within the limits of the connected capacity determined by the agreement, the quality and parameters of which must comply with technical regulations and other mandatory requirements.

When accessing services for the transmission of electrical energy in conditions of limited capacity of electrical networks, the possibility of charging additional fees is excluded.

31. Restriction of the right to receive electrical energy is possible only in the event of a deviation from the normal operating modes of the electrical network caused by emergencies and (or) the removal of electrical power facilities for repairs or out of operation and leading to a power shortage.

At the same time, the limitation of electrical energy consumption is carried out in accordance with acts of approval of emergency and technological armor.

32. The capacity of the electrical network is determined according to the design scheme of the Unified Energy System of Russia, developed by the system operator together with the organization for managing the unified national (all-Russian) electrical network, taking into account the forecast balances of electrical energy and power. When carrying out such calculations, repair schedules for main generating equipment (agreed with generating companies), equipment for electrical substations and power lines, and power receiving equipment for electrical energy consumers with a controlled load are also taken into account.

The system operator and the organization for managing the unified national (all-Russian) electrical grid communicate to market participants information about the limitations of the capacity of the electrical network, including the results of these calculations.

IV. The procedure for setting tariffs for electric energy transmission services, providing for taking into account the degree of use of power of the electric network

33. Tariffs for services for the transmission of electrical energy are established taking into account the use by consumers of these services of the power of the electrical network to which they are directly technologically connected.

34. The consumer of services must notify the network organization at least 6 months before the next period of tariff regulation about the amount of declared capacity for the coming calendar year, which reflects the degree of use of power of the electrical network by the consumer of services.

The amount of declared power is determined for each point of connection and cannot exceed the maximum connected power at the corresponding point of connection to the network of this service consumer.

In the absence of the specified notification about the value of the declared power, when setting tariffs, the value of the maximum connected power of the power receiving device (power installation) of the service consumer is accepted.

When determining the basis for setting tariffs for the next regulation period, the grid organization has the right to use in relation to consumers of services that systematically exceed the amount of declared power, the amount of power declared by the consumer for the next regulation period or the actual amount of power used for the past period.

35. Tariffs for services for the transmission of electrical energy are established in accordance with the principles of pricing for electrical and thermal energy in the Russian Federation and the rules of state regulation and application of tariffs for electrical and thermal energy in the Russian Federation, taking into account paragraph 34 of these Rules.

Taking into account the degree of power utilization of the electric network when determining the tariff for electric energy transmission services is carried out in accordance with the methodological instructions approved by the federal executive body on tariffs.

V. The procedure for determining losses in electrical networks and paying for these losses

36. Actual losses of electrical energy in electrical networks are defined as the difference between the volume of electrical energy supplied to the electrical network from other networks or from electricity producers, and the volume of electrical energy consumed by power receiving devices connected to this network, as well as transmitted to other networks organizations.

37. Grid organizations are obliged to compensate for actual losses of electrical energy that occurred in their network facilities, minus the losses included in the price of electrical energy.

38. Consumers of services, with the exception of producers of electrical energy, are required to pay, as part of the fee for services for the transmission of electrical energy, regulatory losses arising during the transmission of electrical energy through the network of a network organization with which the relevant persons have concluded an agreement, with the exception of losses included in the price (tariff) for electrical energy, in order to avoid double metering. Consumers of services pay for losses of electrical energy in excess of the standard if it is proven that the losses arose through the fault of these consumers of services.

39. The amount of electrical energy losses in electrical networks, which is included in the fee for services for the transmission of electrical energy, is determined based on the standard for electrical energy losses. Loss standards are established by the authorized federal executive body in accordance with these Rules and the methodology for determining standard and actual losses of electrical energy in electrical networks.

40. Standards for losses of electrical energy in electrical networks are established in relation to the totality of power transmission lines and other electrical grid facilities belonging to the relevant network organization, taking into account differentiation by network voltage levels when setting tariffs for services for the transmission of electrical energy.

41. The methodology for determining standard and actual losses of electrical energy in electrical networks should provide for the calculation of losses based on:

technical characteristics of power lines and other power grid facilities that determine the amount of variable losses in accordance with the technology of transmission and conversion of electrical energy;

standard conditionally constant losses for power lines, power transformers and other power grid facilities;

standard losses in electrical energy measuring instruments.

When establishing standards, the technical condition of power lines and other power grid facilities may also be taken into account.

42. The organization for managing the unified national (all-Russian) electrical network buys electrical energy in order to compensate for losses in its networks on the wholesale electrical energy market.

Territorial grid organizations and other owners of electric grid facilities included in the unified national (all-Russian) electric grid, if they are not subjects of the wholesale electric energy (power) market, purchase electric energy in order to compensate for losses in their networks on the retail electric power market. energy under a contract for the purchase and sale (supply) of electrical energy concluded with a guaranteeing supplier (energy sales organization) operating in the territory where the relevant electrical networks are located.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

VI. The procedure for provision and disclosure by network organizations of information on the capacity of electrical networks, their technical characteristics and the cost of services for the transmission of electrical energy

43. Information about the capacity of electrical networks and their technical characteristics is disclosed by the network organization in accordance with the standards for the disclosure of information by subjects of the wholesale and retail electricity markets.

44. The network organization discloses information on the technical characteristics of electrical networks quarterly no later than 30 working days from the end of the quarter.

45. The network organization is obliged to provide information on the availability of capacity of electrical networks and on the cost of services for the transmission of electrical energy upon request (in writing) of the service consumer.

46. ​​The requested information must be provided within 7 days from the date of receipt of the request with reimbursement by the service consumer of the costs of its provision actually incurred by the network organization.

47. Documents containing the requested information must be prepared in accordance with the established procedure by network organizations.

48. The grid organization is responsible for the timeliness, completeness and accuracy of the information provided and disclosed in the manner established by the legislation of the Russian Federation.

VII. The procedure for considering applications (complaints) regarding the provision of access to services for the transmission of electrical energy and making decisions on these applications (complaints) that are binding on legal entities and individuals

49. The basis for initiating and considering cases on issues of providing access to services for the transmission of electrical energy, making decisions and issuing orders by the antimonopoly authority are statements of government authorities or statements (complaints) of legal entities and individuals.

50. The application (complaint) must contain information about the applicant and the person against whom the application (complaint) was filed, a description of the violation of the requirements of these Rules, as well as the demands that the applicant is making.

51. The antimonopoly authority considers the application (complaint) within a month from the date of its receipt.

In case of insufficiency or absence of evidence allowing one to come to a conclusion about the presence or absence of signs of violation of the requirements of these Rules, the antimonopoly authority has the right to collect and analyze additional evidence to extend the period for consideration of the application (complaint) to 3 months from the date of its receipt. The antimonopoly authority is obliged to notify the applicant in writing about the extension of the period for consideration of the application (complaint).

52. If there are no signs of violation of the requirements of these Rules and antimonopoly legislation, the antimonopoly authority notifies the applicant in writing within 10 days from the date of the decision.

53. Cases of violations of antimonopoly legislation are considered by the antimonopoly authority in accordance with the legislation of the Russian Federation.

54. The consideration of cases of violations of the requirements of these Rules in terms of providing access to services for the transmission of electrical energy and antimonopoly legislation and the adoption of decisions (instructions) on them are carried out in the manner established by the federal antimonopoly body.

55. Federal executive authorities, executive authorities of constituent entities of the Russian Federation, local governments, other bodies or organizations (their officials) vested with the functions or rights of these authorities, commercial and non-profit organizations (their heads), individuals, including including individual entrepreneurs, have the right to appeal decisions and orders in whole or in part of the antimonopoly authority in the manner established by the legislation of the Russian Federation.

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

RULES FOR NON-DISCRIMINATIVE ACCESS TO OPERATIONAL DISPATCH CONTROL SERVICES IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES

1. These Rules define the general principles and procedure for ensuring non-discriminatory access of subjects of the electric power industry (hereinafter - consumers of services) to services for operational dispatch control in the electric power industry (hereinafter - services) provided by the system operator and other subjects of operational dispatch control (hereinafter - system operator ), as well as the procedure for providing these services.

2. These Rules do not apply to relations related to the provision of services by subordinate subjects of operational dispatch control in the electric power industry to higher-level subjects of operational dispatch control in the electric power industry.

3. Non-discriminatory access to services involves ensuring equal conditions for the provision of services to their consumers, regardless of their organizational and legal form and legal relations with the person providing these services.

4. The system operator is obliged to disclose information regarding access to services and the provision of services in accordance with the standards for disclosure of information by subjects of the wholesale and retail electricity markets.

5. The system operator provides the following services:

a) management of technological operating modes of electric power facilities;

b) medium- and long-term forecasting of the volume of production and consumption of electrical energy;

c) participation in the formation of a reserve of production energy capacities;

d) approval of the removal for repair and decommissioning of electrical grid facilities and energy facilities for the production of electrical and thermal energy, as well as their commissioning after repair;

e) development of daily operating schedules for power plants and electrical networks of the Unified Energy System of Russia;

f) regulation of the frequency of electric current, ensuring the functioning of the system for automatic regulation of the frequency of electric current and power, ensuring the functioning of system and emergency automation;

g) organization and management of parallel operation modes of the Unified Energy System of Russia and electric power systems of foreign countries;

h) participation in the formation and issuance of technological requirements for technological connection of electric power industry entities to the unified national (all-Russian) electric grid and territorial distribution networks, ensuring their operation as part of the Unified Energy System of Russia.

6. Services are provided on the basis of a bilateral agreement on the provision of services for operational dispatch control in the electric power industry (hereinafter referred to as the agreement), as well as on the basis of an agreement on joining the trading system of the wholesale electricity market.

7. The consumer of services can simultaneously be a participant in the contracts specified in paragraph 6 of these Rules only under the following conditions:

the provisions of these agreements regarding the provision of services are completely identical;

the total cost of services provided on the basis of these contracts is determined by the tariffs established by the federal executive body on tariffs.

8. The conclusion of an agreement between the service consumer and the system operator is mandatory for both parties.

9. Wholesale market entities enter into an agreement with the system operator before they enter into an agreement with the organization managing the unified national (all-Russian) electrical network for the provision of services for the transmission of electrical energy through the unified national (all-Russian) electrical network.

10. The price of services is determined by the tariffs established by the federal executive body on tariffs.

11. The consumer of services who intends to conclude an agreement (hereinafter referred to as the applicant) sends to the system operator an application in writing for access to services, which must contain the following information:

details of the service consumer;

points of connection to networks of a network organization;

start dates for services.

The applicant, along with the application, has the right to send the system operator a draft agreement.

12. The system operator, within 30 days from the date of receipt of the application for access to services, is obliged to consider it and make a decision on providing access to services or refusing it.

13. In the absence of the information specified in paragraph 11 of these Rules, the system operator notifies the applicant about this within 3 days and, within 30 days from the date of receipt of the missing information, considers the application for access to services in accordance with paragraph 12 of these Rules.

14. If a decision is made to provide access to services, the system operator is obliged to send the applicant a signed draft agreement.

15. The applicant, who has received a signed draft agreement from the system operator and has no objections to its terms, fills out the agreement in the part related to information about the applicant and sends 1 signed copy of the agreement to the system operator.

16. If the applicant has submitted a draft agreement, and the system operator has no objections to its terms, the latter is obliged to sign it and send 1 signed copy of the agreement to the applicant.

The agreement is considered concluded from the date of its signing by both parties, unless otherwise established by this agreement or a court decision.

17. If a decision is made to refuse to provide access to services, the system operator is obliged to send the applicant a notice in writing and documents justifying the refusal no later than 10 days from the date of receipt of the application specified in paragraph 11 of these Rules.

A refusal to provide access to services may be appealed to the antimonopoly authority and (or) challenged in court.

18. The system operator has the right to refuse to provide access to services in the following cases:

a) the applicant did not provide the information provided for in paragraph 11 of these Rules;

b) the applicant provided false information;

c) the applicant’s energy facilities are located outside the area of ​​his dispatch responsibility.

In this case, the applicant has the right to re-apply to the system operator with an application for access to services. If the grounds for refusal are eliminated, the system operator does not have the right to refuse to provide the applicant with access to services.

19. The provision of services is carried out in order to ensure reliable energy supply and quality of electrical energy that meets the requirements of technical regulations and other mandatory requirements established by regulatory legal acts, and to take measures to ensure the fulfillment of obligations of electricity industry entities under contracts concluded on the wholesale and retail markets of electrical energy.

As part of the provision of services, the system operator is obliged to choose the most cost-effective solution that ensures the safe and trouble-free operation of the technological infrastructure of the electric power industry and the quality of electrical energy that meets the requirements of technical regulations and other mandatory requirements.

20. Consumers of services have the right not to execute operational dispatch commands and orders if their execution poses a threat to human life, the safety of equipment or leads to a violation of the limits and conditions for the safe operation of nuclear power plants.

21. In the event of emergency electrical power conditions, the provision of services is carried out taking into account the specifics established by the legislation of the Russian Federation.

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

RULES OF NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES

1. These Rules define the general principles and procedure for ensuring non-discriminatory access of subjects of the wholesale electricity (capacity) market (hereinafter - subjects of the wholesale market) to services for organizing the functioning of the trading system of the wholesale electricity (capacity) market, organizing wholesale trade in electrical energy and conducting reconciliation and offsetting mutual counter obligations of trading participants (hereinafter referred to as the services) of the administrator of the wholesale market trading system (hereinafter referred to as the administrator), as well as the procedure for providing these services.

2. Non-discriminatory access to administrator services provides for equal conditions for the provision of services to subjects of the wholesale market, regardless of their organizational and legal form and legal relations with the person providing these services.

3. The administrator is obliged to disclose information regarding access to services and their provision in accordance with the standards for disclosure of information by subjects of the wholesale and retail electricity markets.

4. The administrator does not have the right to refuse to provide services to subjects of the wholesale market, except for the cases established by these Rules and the rules of the wholesale electricity market.

5. Administrator services can be provided to the following persons:

included in the list of commercial organizations - subjects of the federal (all-Russian) wholesale electricity (capacity) market, electricity tariffs for which are established by the federal executive body on tariffs, before the rules of the wholesale electricity market come into force;

having received the status of a wholesale market entity in accordance with the rules of the wholesale electricity market by providing the administrator with the documents and information specified in these Rules, and the wholesale market entities signing an agreement on joining the trading system of the wholesale electricity (capacity) market.

6. A legal entity wishing to gain access to the services of an administrator (hereinafter referred to as the applicant) must submit an application for this and submit the following documents to the administrator:

information about the type of wholesale market entity (generating company, energy sales organization, energy supply organization, supplier of last resort, electricity consumer, etc.) to which the applicant corresponds, in accordance with the rules of the wholesale electricity (capacity) market of the transition period;

signed by the authorized person of the applicant, 5 copies of the draft agreement on joining the wholesale electricity (power) market to the trading system in the form approved by the administrator;

the applicant's application form in the prescribed form;

notarized copies of constituent documents;

a notarized copy of the certificate of state registration of a legal entity;

a notarized copy of the certificate of registration of the applicant with the tax authorities of the Russian Federation;

documents confirming the powers of persons representing the interests of the applicant;

a document confirming the assignment of the organization to the status of a guaranteeing supplier in cases and in the manner established by the legislation of the Russian Federation;

a single-line diagram of connection to an external electrical network, agreed upon with the owner or other legal owner of the network facilities to which the applicant or third parties whose interests he represents are technologically connected, indicating the names and voltage levels of the buses of external substations, proposed groups of delivery points, and places of connection of devices commercial metering, voltage measuring transformers and balance sheet boundaries certified by representatives of adjacent owners of electrical networks;

acts of delimitation of balance sheet ownership and operational responsibility, agreed upon with the owners or other legal owners of network facilities to which the applicant or third parties whose interests the applicant intends to represent are technologically connected.

An applicant who has the right to purchase and sell electrical energy (power) in the regulated sector is required to submit to the administrator a document confirming the inclusion of the legal entity in the list of commercial organizations - subjects of the federal (all-Russian) wholesale electrical energy (capacity) market, the tariffs for electrical energy for which are established by the federal executive body on tariffs.

In order to confirm the compliance of generating and energy-receiving equipment with the quantitative characteristics presented for facilities participating in the wholesale electricity market, the applicant submits to the administrator the passport technological characteristics of the specified equipment.

7. An applicant representing the interests of third parties in the wholesale electricity (capacity) market provides the administrator with information on the technological characteristics of the generating equipment of the suppliers whose interests he represents, and (or) the technological characteristics of the energy receiving equipment of the consumers whose interests he represents.

An applicant carrying out activities in the transmission of electrical energy and purchasing electrical energy on the wholesale electrical energy (power) market, in order to compensate for losses in electrical networks, submits to the administrator the characteristics of the electrical network and network facilities for each group of supply points (network facility).

In order to obtain data on the actual production and consumption of energy, as well as to carry out settlements on the wholesale electricity (capacity) market, the applicant submits documents indicating that the commercial accounting system complies with the mandatory technical requirements and the terms of the agreement on joining the trading system of the wholesale electricity (capacity) market ), in a manner determined by the administrator.

All documents must be submitted by the applicant in accordance with the requirements determined by the administrator.

The administrator has no right to demand the provision of information not provided for by these Rules, unless otherwise established by the legislation of the Russian Federation.

In order to ensure equal access to the administrator’s services, the owner or other legal owner of network facilities to which the applicant or third parties whose interests he represents is technologically connected is obliged to ensure approval of a single-line connection diagram to the external electrical network and draw up acts of delimitation of balance sheet responsibility.

8. The administrator has the right to refuse access to the administrator’s services if the applicant:

a) did not submit the documents and information provided for in paragraph 6 of these Rules;

b) provided false information;

c) does not comply with any of the requirements established by the legislation of the Russian Federation for subjects of the wholesale market.

The applicant has the right to re-apply to the administrator for access to the administrator’s services if the grounds for denying the applicant access to the administrator’s services are eliminated.

9. The decision to deny access to the administrator’s services may be appealed in the manner established by the legislation of the Russian Federation.

10. The administrator provides services to subjects of the wholesale market on the basis of an agreement on joining the trading system of the wholesale electricity market.

A signed copy of the agreement on joining the trading system of the wholesale electricity (power) market is sent by the administrator to the wholesale market entity.

11. Administrator services are paid by the wholesale market entity at tariffs approved by the federal executive body for tariffs.

12. In the event of non-payment of administrator services by a wholesale market entity, the administrator has the right to suspend the acceptance of applications from a wholesale market entity to participate in the procedure for competitive selection of price applications in the free trade sector of the wholesale market until the debt is fully repaid.

13. The administrator has the right to stop providing services to a wholesale market entity in the event of:

non-compliance of a legal entity with the requirements for a wholesale market entity;

loss of the status of a wholesale market entity by a legal entity;

repeated failure or improper fulfillment by a wholesale market entity of obligations to pay for administrator services;

termination of the agreement on joining the wholesale market trading system;

termination of the activities of a wholesale market entity on the grounds provided for by the legislation of the Russian Federation.

14. The adoption by the administrator, in accordance with the rules of the wholesale electricity (power) market of the transition period and the agreement on joining the trading system of the wholesale electricity market, of a decision to recognize the sale (purchase) of electricity in the free trade sector in general or in any limited territory failed cannot be considered as non-fulfillment or improper fulfillment of obligations to provide administrator services.

APPROVED
Government Decree
Russian Federation
dated December 27, 2004
N 861

RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEPTION DEVICES (POWER INSTALLATIONS) OF LEGAL AND INDIVIDUALS TO ELECTRIC NETWORKS

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

I. General provisions

1. These Rules determine the procedure for technological connection of energy receiving devices (power installations) of legal entities and individuals (hereinafter referred to as energy receiving devices), regulate the procedure for technological connection, determine the essential terms of the agreement on the implementation of technological connection to electrical networks (hereinafter referred to as the agreement), establish requirements for issuance of individual technical conditions for connection to electrical networks (hereinafter referred to as technical conditions) and criteria for the presence (absence) of the technical possibility of technological connection.

2. These Rules apply to persons whose power receiving devices were previously connected to the electrical network and who declared the need to review (increase) the amount of connected power.

3. The grid organization is obliged to carry out, in relation to any person who contacts it, measures for the technological connection of newly commissioned, newly built, expanding their previously connected capacity and reconstructed power receiving devices to their electrical networks (hereinafter referred to as technological connection), subject to their compliance with these Rules and the availability of technical capabilities for technological connection.

In relation to power receiving devices technologically connected to the electrical network before the entry into force of these Rules, the contract is not concluded and the measures specified in paragraph 12 of these Rules are not carried out.

4. Any persons have the right to technological connection of power transmission lines they have built to electrical networks in accordance with these Rules.

5. When connecting power plants to the distribution devices of a power plant, the latter performs the functions of a network organization in terms of carrying out activities under the contract.

6. Technological connection is carried out on the basis of an agreement concluded with the grid organization within the time limits established by these Rules. The conclusion of an agreement is mandatory for a network organization. In the event of an unjustified refusal or evasion by a network organization from concluding a contract, the interested party has the right to file a claim in court to compel the conclusion of the contract and to recover damages caused by such an unjustified refusal or evasion.

7. These Rules establish the following procedure for technological connection:

filing an application for technological connection with a requirement to issue technical specifications;

preparation of technical specifications and submission of a draft agreement including technical specifications;

conclusion of an agreement;

compliance with technical conditions on the part of the connected person and on the part of the network organization;

performing actions to connect and ensure operation of the power receiving device in the electrical network;

checking compliance with technical conditions and drawing up an act on technological connection.

II. The procedure for concluding and fulfilling the contract

8. To obtain technical conditions and carry out technological connection, the person who owns the power receiving device sends an application for technological connection (hereinafter referred to as the application) to the network organization to whose electrical network the technological connection is planned.

9. The application must include the following information:

a) full name of the applicant;

b) location of the applicant;

c) the postal address of the applicant;

d) a plan for the location of the power receiving device in relation to which it is planned to carry out measures for technological connection;

e) maximum power of the energy receiving device and its technical characteristics, number, power of generators and transformers connected to the network;

f) the number of points of connection to the electrical network, indicating the technical parameters of the elements of electrical installations connected at specific points of the electrical network;

g) a single-line diagram of the applicant’s electrical networks connected to the networks of the grid organization, indicating the possibility of redundancy from its own energy supply sources (including redundancy of its own needs) and the possibility of switching loads (generation) through the applicant’s internal networks;

h) the declared level of reliability of the power receiving device;

i) the nature of the load of the electrical energy consumer (for generators - the possible speed of increasing or decreasing the load) and the presence of loads that distort the shape of the electric current curve and cause voltage asymmetry at connection points;

j) the value and justification of the value of the technological minimum (for generators) and emergency armor (for consumers of electrical energy);

k) permission from the authorized state supervision body to allow the power receiving device into operation (except for facilities under construction);

l) the scope of possible participation in automatic or operational emergency power control (for power plants and consumers, with the exception of individuals) in the provision of services in accordance with a separate agreement;

m) the scope of possible participation in normalized primary frequency regulation and secondary power regulation (for power plants) in the provision of services in accordance with a separate agreement;

o) list and capacity of consumer's current collectors (except for individuals), which can be turned off using an emergency automatic device.

The list of information provided in the application is exhaustive.

The grid organization has no right to demand the provision of information not provided for by these Rules.

10. The grid organization is obliged to send a draft agreement to the applicant for approval within 30 days from the date of receipt of the application.

If the information specified in paragraph 9 of these Rules is missing, or is provided incompletely, the network organization notifies the applicant within 6 working days and considers the application within 30 days from the date of receipt of the missing information.

If the technological connection of power receiving devices is particularly complex for the organization managing the unified national (all-Russian) electrical network or other owners of such network facilities, the specified period by agreement of the parties can be increased to 90 days. The applicant is notified of the increase in the period and the reasons for its change.

11. The agreement must contain the following essential conditions: measures for technological connection and the obligations of the parties to implement them;

fulfillment of technical conditions;

deadlines for the grid organization to carry out technological connection activities;

the amount of fees for carrying out technological connection activities;

responsibility of the parties for fulfilling the terms of the agreement;

boundaries of delineation of balance sheet ownership.

12. Activities for technological connection include:

a) development of a power supply scheme;

b) technical inspection (inspection) of connected power receiving devices by an authorized government body with the participation of representatives of the network organization;

c) preparation and issuance of technical specifications;

d) fulfillment of technical conditions (on the part of the person whose power receiving device is connected, and on the part of the network organization), including the implementation by the network organization of measures to equip power receiving devices with relay protection devices, emergency and regime automation in accordance with the technical conditions;

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

e) actual actions to connect and ensure operation of the power receiving device in the electrical network;

f) checking compliance with technical conditions and drawing up an act on technological connection.

The list of activities for technological connection is exhaustive.

It is prohibited to impose services not provided for by these Rules on a person interested in technological connection.

13. The network organization is obliged, within 30 days from the date of receipt of the application, to consider it, prepare technical conditions for technological connection and agree on them with the system operator (subject of operational dispatch control), and the organization for managing the unified national (all-Russian) electrical network or other owners objects of such a network in the cases provided for in paragraph three of clause 10 of these Rules - within 90 days.

The grid organization is obliged, within 5 days from the date of receipt of the application, to send a copy of it for consideration by the system operator (subject of operational dispatch control), and then, together with him, review it and prepare technical conditions for technological connection.

14. Technical conditions for technological connection are an integral part of the contract.

The technical specifications must indicate:

a) circuits for issuing or receiving power and points of connection to the electrical network (power lines or base substations);

b) justified requirements for strengthening the existing electrical network in connection with the connection of new capacities (construction of new power lines, substations, increasing the cross-section of wires and cables, increasing the capacity of transformers, expanding distribution devices, installing compensating devices to ensure the quality of electricity);

c) calculated values ​​of short circuit currents, requirements for relay protection, voltage regulation, emergency automation, telemechanics, communications, insulation and overvoltage protection, as well as for electrical energy and power metering devices in accordance with the requirements established by regulatory legal acts;

d) requirements for equipping power plants with emergency automatic equipment for issuing power and for equipping consumers with emergency automatic devices;

e) requirements for equipping with devices that ensure the participation of power plants or consumers in automatic or operational emergency power control in the provision of services in accordance with a separate contract;

f) requirements for equipping with devices that ensure the participation of power plants in normalized primary frequency regulation and in secondary power regulation in the provision of services in accordance with a separate agreement;

g) requirements for equipping power receiving devices with relay protection devices, emergency and regime automation, including the placement of devices that provide remote input of temporary power outage schedules from dispatch centers in accordance with the requirements of the relevant operational dispatch control entity.

(as amended by Decree of the Government of the Russian Federation dated August 31, 2006 N 530)

III. Criteria for the presence (absence) of technical possibility of technological connection

15. The criteria for the availability of technical possibility of technological connection are:

a) the location of the power receiving device, in respect of which an application for technological connection has been submitted, within the territorial boundaries of service of the corresponding network organization;

b) no restrictions on connected power in the network node to which the technological connection is to be made.

If any of the specified criteria is not met, there is no technical possibility of technological connection.

In order to verify the validity of the network organization’s determination of the lack of technical feasibility, the applicant has the right to apply to the authorized federal executive body for technological supervision to obtain an opinion on the presence (absence) of the technical possibility of technological connection by the network organization.

16. Restrictions on the connection of additional power arise if the full use of the consumed (generating) power of all previously connected consumers of services for the transmission of electrical energy and the power of the newly connected power receiving device can lead to the load of the energy equipment of the network organization exceeding the values ​​​​defined by technical standards and standards approved or adopted in the manner established by the legislation of the Russian Federation.

17. If there is a restriction on connecting new power, it is allowed to connect power receiving devices to electrical networks within the power value that does not cause restrictions on the use of consumed (generating) power of all electrical energy consumers previously connected to a given network node, or in the declared volume in agreement with the specified consumers.

The website “Zakonbase” contains the RF Government Decree dated December 27, 2004 N 861 (as amended on August 31, 2006) “ON APPROVAL OF THE RULES OF NON-DISCRIMINATIONAL ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, NON-DISCRIMINATION RULES FULL ACCESS TO OPERATIONS AND DISPATCH MANAGEMENT SERVICES IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES, THE RULES OF NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES AND THE RULES FOR THE TECHNOLOGICAL CONNECTION OF ENERGY RECEIVING DEVICES (ENER GETICAL INSTALLATIONS) OF LEGAL AND INDIVIDUALS TO ELECTRICAL NETWORKS" in the most recent edition. It is easy to comply with all legal requirements if you read the relevant sections, chapters and articles of this document for 2014. To find the necessary legislative acts on a topic of interest, you should use convenient navigation or advanced search.

On the Zakonbase website you will find the RF Government Decree dated December 27, 2004 N 861 (as amended on August 31, 2006) “ON APPROVAL OF THE RULES OF NON-DISCRIMINATIONAL ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, NON-DISCRIMINATION RULES TIONAL ACCESS TO OPERATIONAL DISPATCH SERVICES MANAGEMENT IN THE ELECTRIC POWER INDUSTRY AND THE PROVISION OF THESE SERVICES, RULES OF NON-DISCRIMINATIVE ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND THE PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY CONSUMPTION DEVICES STS (ENERGY INSTALLATIONS) OF LEGAL AND INDIVIDUALS TO ELECTRIC NETWORKS" in a fresh and complete version, in which all changes and amendments. This guarantees the relevance and reliability of the information.

At the same time, download the RESOLUTION of the Government of the Russian Federation dated December 27, 2004 N 861 (as amended on August 31, 2006) “ON APPROVAL OF THE RULES OF NON-DISCRIMINATIVE ACCESS TO ELECTRIC ENERGY TRANSMISSION SERVICES AND THE PROVISION OF THESE SERVICES, RULES OF NON-DISCRIMINATION ACCESS SERVICES FOR OPERATIONAL DISPATCH MANAGEMENT IN THE ELECTRIC POWER INDUSTRY AND PROVISION OF THESE SERVICES, RULES OF NON-DISCRIMINATIONAL ACCESS TO THE SERVICES OF THE ADMINISTRATOR OF THE WHOLESALE MARKET TRADE SYSTEM AND PROVISION OF THESE SERVICES AND RULES FOR TECHNOLOGICAL CONNECTION OF ENERGY RECEIVING DEVICES (YURI POWER INSTALLATIONS) INDIVIDUALS AND INDIVIDUALS TO ELECTRICAL NETWORKS" is available completely free of charge, both in full and in separate chapters.